Physical Progress
46.8%
Drone-monitored
Financial Progress
41.6%
Of awarded cost
Awarded Cost
₹1158 Cr
Contract value
Length
55.002 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4519
Aerial captures
Stage
Under Construction (AD issued)
Due Date
29-03-2025
Likely Date
30-07-2027
46.8%
Physical Done
Awarded
31-03-2023
Construction Started
31-03-2023
In Progress
Near Completion
-
Completed
30-07-2027
UPC
N/05005/08001/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
55.002 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4519 frames
Last Flight
2026-05-26
Awarded Cost
₹1157.50 Cr
Capital Cost
₹1390.92 Cr
Start Date
31-03-2023
PCOD Date
-
Scheduled Completion
29-03-2025
Likely Completion
30-07-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 09:36:24
Megha Engineering and Infrastructure Ltd.
Physical progress stands at 46.8%. Financial utilization at 41.6%.
Project is on schedule or ahead of planned completion date.
Covers 55.002 km on 119D, improving regional connectivity.
4519 drone frames uploaded — real-time aerial monitoring is active for this project.
4,519 frames · NHAI surveillance footage · UPC N/05005/08001/BR