All NHAI Projects
119DHAM 2922 Drone Frames

4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I)

UPC: N/05005/08001/BR

Physical Progress

54.8%

Drone-monitored

Financial Progress

50.0%

Of awarded cost

Awarded Cost

₹1158 Cr

Contract value

Length

55.002 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2922

Aerial captures

Project Progress

Physical Progress54.8%
Financial Progress50.0%

Stage

Under Construction (AD issued)

Due Date

29-03-2025

Likely Date

30-07-2027

Completion

54.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

31-03-2023

Construction Started

31-03-2023

In Progress

Near Completion

-

Completed

30-07-2027

Physical vs Financial Progress

Project Details

UPC

N/05005/08001/BR

National Highway

119D

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

55.002 km

Contractor

Megha Engineering and Infrastructure Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

2922 frames

Last Flight

2026-07-26

Cost & Timeline

Awarded Cost

₹1157.50 Cr

Capital Cost

₹1390.92 Cr

Start Date

31-03-2023

PCOD Date

-

Scheduled Completion

29-03-2025

Likely Completion

30-07-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-29 01:29:50

Contractor Profile

Megha Engineering and Infrastructure Ltd.

RO-Patna119DHAM

Project Intelligence

1

Project is more than halfway complete at 54.8% physical progress.

2

Project is on schedule or ahead of planned completion date.

3

Covers 55.002 km on 119D, improving regional connectivity.

4

2922 drone frames uploaded — real-time aerial monitoring is active for this project.

4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1157.50 Cr and is currently ongoing with physical progress at 54.8%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,922 frames · NHAI surveillance footage · UPC N/05005/08001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of N"?
Current physical progress: 54.8%. Financial progress: 50.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 29-03-2025. Likely completion: 30-07-2027.
QWho is the contractor for this NHAI highway project?
The contractor for 4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 55.002 km on 119D.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1157.50 Crore. Total capital cost: ₹1390.92 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05005/08001/BR in NHAI?
UPC (Unique Project Code) N/05005/08001/BR refers to "4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.