4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I)
Physical Progress
46.8%
Drone-monitored
Financial Progress
41.6%
Of awarded cost
Awarded Cost
₹1158 Cr
Contract value
Length
55.002 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4519
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
29-03-2025
Likely Date
30-07-2027
Completion
46.8%
Physical Done
Project Timeline
Awarded
31-03-2023
Construction Started
31-03-2023
In Progress
Near Completion
-
Completed
30-07-2027
Physical vs Financial Progress
Project Details
UPC
N/05005/08001/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
55.002 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4519 frames
Last Flight
2026-05-26
Cost & Timeline
Awarded Cost
₹1157.50 Cr
Capital Cost
₹1390.92 Cr
Start Date
31-03-2023
PCOD Date
-
Scheduled Completion
29-03-2025
Likely Completion
30-07-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 09:36:24
Contractor Profile
Megha Engineering and Infrastructure Ltd.
Project Intelligence
Physical progress stands at 46.8%. Financial utilization at 41.6%.
Project is on schedule or ahead of planned completion date.
Covers 55.002 km on 119D, improving regional connectivity.
4519 drone frames uploaded — real-time aerial monitoring is active for this project.
4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1157.50 Cr and is currently **ongoing** with physical progress at 46.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,519 frames · NHAI surveillance footage · UPC N/05005/08001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of N"?
- Current physical progress: 46.8%. Financial progress: 41.6%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 29-03-2025. Likely completion: 30-07-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 55.002 km on 119D.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1157.50 Crore. Total capital cost: ₹1390.92 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/05005/08001/BR in NHAI?
- UPC (Unique Project Code) N/05005/08001/BR refers to "4L Greenfield Alignment of Amas to Shivrampur from 0.000 Km. to 55.002 Km. of NH 119 D (Pkg-I)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.