4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)

UPC: N/05005/08002/BR

Physical Progress

50.8%

Drone-monitored

Financial Progress

48.0%

Of awarded cost

Awarded Cost

₹1207 Cr

Contract value

Length

54.322 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

5082

Aerial captures

Project Progress

Physical Progress50.8%
Financial Progress48.0%

Stage

Under Construction (AD issued)

Due Date

03-07-2025

Likely Date

30-11-2027

Completion

50.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

04-07-2023

Construction Started

04-07-2023

In Progress

Near Completion

-

Completed

30-11-2027

Physical vs Financial Progress

Project Details

UPC

N/05005/08002/BR

National Highway

119D

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

54.322 km

Contractor

Megha Engineering and Infrastructure Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

5082 frames

Last Flight

2026-07-27

Cost & Timeline

Awarded Cost

₹1207.00 Cr

Capital Cost

₹1494.31 Cr

Start Date

04-07-2023

PCOD Date

-

Scheduled Completion

03-07-2025

Likely Completion

30-11-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-08-28 23:23:57

Contractor Profile

Megha Engineering and Infrastructure Ltd.

RO-Patna119DHAM

Project Intelligence

1

Project is more than halfway complete at 50.8% physical progress.

2

Project is on schedule or ahead of planned completion date.

3

Covers 54.322 km on 119D, improving regional connectivity.

4

5082 drone frames uploaded — real-time aerial monitoring is active for this project.

4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1207.00 Cr and is currently ongoing with physical progress at 50.8%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

5,082 frames · NHAI surveillance footage · UPC N/05005/08002/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.30"?
Current physical progress: 50.8%. Financial progress: 48.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 03-07-2025. Likely completion: 30-11-2027.
QWho is the contractor for this NHAI highway project?
The contractor for 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 54.322 km on 119D.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1207.00 Crore. Total capital cost: ₹1494.31 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05005/08002/BR in NHAI?
UPC (Unique Project Code) N/05005/08002/BR refers to "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.