Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /NHAI Drone Tracker
  3. /4L Greenfield Alignment of Shivrampur to Ramnagar
All NHAI Projects
119DHAMRoad Infrastructure 9872 Drone Frames

4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)

UPC: N/05005/08002/BR

Physical Progress

44.8%

Drone-monitored

Financial Progress

41.1%

Of awarded cost

Awarded Cost

₹1207 Cr

Contract value

Length

54.322 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

9872

Aerial captures

Project Progress

Physical Progress44.8%
Financial Progress41.1%

Stage

Under Construction (AD issued)

Due Date

03-07-2025

Likely Date

30-11-2027

Completion

44.8%

Physical Done

DoneRemaining

Project Timeline

Awarded

04-07-2023

Construction Started

04-07-2023

In Progress

Near Completion

-

Completed

30-11-2027

Physical vs Financial Progress

Project Details

UPC

N/05005/08002/BR

National Highway

119D

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

54.322 km

Contractor

Megha Engineering and Infrastructure Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

9872 frames

Last Flight

2026-02-23

Cost & Timeline

Awarded Cost

₹1207.00 Cr

Capital Cost

₹1494.31 Cr

Start Date

04-07-2023

PCOD Date

-

Scheduled Completion

03-07-2025

Likely Completion

30-11-2027

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 08:06:55

Contractor Profile

Megha Engineering and Infrastructure Ltd.

RO-Patna119DHAM

Project Intelligence

1

Physical progress stands at 44.8%. Financial utilization at 41.1%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 54.322 km on 119D, improving regional connectivity.

4

9872 drone frames uploaded — real-time aerial monitoring is active for this project.

Drone Imagery Available

9,872 frames · NHAI surveillance footage · UPC N/05005/08002/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.30"?
Current physical progress: 44.8%. Financial progress: 41.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 03-07-2025. Likely completion: 30-11-2027.
Who is the contractor for this NHAI highway project?
The contractor for 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 54.322 km on 119D.
What is the cost of this NHAI highway project?
The awarded cost is ₹1207.00 Crore. Total capital cost: ₹1494.31 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/05005/08002/BR in NHAI?
UPC (Unique Project Code) N/05005/08002/BR refers to "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.

Related Resources

NHAI

NHAI Drone Tracker Dashboard

Real-time drone progress for all NHAI Bihar projects

RCD

Bihar RCD PMIS

State road and bridge project tracker

Roads

Bihar Road Network Map

GIS map of all Bihar highways and roads

Projects

Bihar Infrastructure Projects

All government infrastructure projects

IPM

IPM Central Project Monitor

Central government projects in Bihar

Tenders

Bihar Government Tenders

Procurement notices including road contracts

BRPNNL

BRPNNL Bridge Projects

Bihar bridge and road project monitor

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure