4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)
Physical Progress
50.8%
Drone-monitored
Financial Progress
48.0%
Of awarded cost
Awarded Cost
₹1207 Cr
Contract value
Length
54.322 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
5082
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
03-07-2025
Likely Date
30-11-2027
Completion
50.8%
Physical Done
Project Timeline
Awarded
04-07-2023
Construction Started
04-07-2023
In Progress
Near Completion
-
Completed
30-11-2027
Physical vs Financial Progress
Project Details
UPC
N/05005/08002/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
54.322 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
5082 frames
Last Flight
2026-07-27
Cost & Timeline
Awarded Cost
₹1207.00 Cr
Capital Cost
₹1494.31 Cr
Start Date
04-07-2023
PCOD Date
-
Scheduled Completion
03-07-2025
Likely Completion
30-11-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-08-28 23:23:57
Contractor Profile
Megha Engineering and Infrastructure Ltd.
Project Intelligence
Project is more than halfway complete at 50.8% physical progress.
Project is on schedule or ahead of planned completion date.
Covers 54.322 km on 119D, improving regional connectivity.
5082 drone frames uploaded — real-time aerial monitoring is active for this project.
4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1207.00 Cr and is currently ongoing with physical progress at 50.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
5,082 frames · NHAI surveillance footage · UPC N/05005/08002/BR
Frequently Asked Questions
- QWhat is the current status of the NHAI project "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.30"?
- Current physical progress: 50.8%. Financial progress: 48.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 03-07-2025. Likely completion: 30-11-2027.
- QWho is the contractor for this NHAI highway project?
- The contractor for 4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 54.322 km on 119D.
- QWhat is the cost of this NHAI highway project?
- The awarded cost is ₹1207.00 Crore. Total capital cost: ₹1494.31 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
- QWhat is UPC N/05005/08002/BR in NHAI?
- UPC (Unique Project Code) N/05005/08002/BR refers to "4L Greenfield Alignment of Shivrampur to Ramnagar from Km. 55.002 to Km. 109.300 of NH 119 D (Pkg-II)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.