4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D
Physical Progress
25.8%
Drone-monitored
Financial Progress
24.3%
Of awarded cost
Awarded Cost
₹1688 Cr
Contract value
Length
42.21 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
8212
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
10-03-2026
Likely Date
30-03-2028
Completion
25.8%
Physical Done
Project Timeline
Awarded
11-03-2024
Construction Started
11-03-2024
In Progress
Near Completion
-
Completed
30-03-2028
Physical vs Financial Progress
Project Details
UPC
N/05005/08004/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
42.21 km
Contractor
Ram Kripal Singh Construction Pvt. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
8212 frames
Last Flight
2026-02-24
Cost & Timeline
Awarded Cost
₹1687.81 Cr
Capital Cost
₹2185.75 Cr
Start Date
11-03-2024
PCOD Date
-
Scheduled Completion
10-03-2026
Likely Completion
30-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 10:01:05
Contractor Profile
Ram Kripal Singh Construction Pvt. Ltd
Project Intelligence
Physical progress stands at 25.8%. Financial utilization at 24.3%.
Project is on schedule or ahead of planned completion date.
Covers 42.21 km on 119D, improving regional connectivity.
8212 drone frames uploaded — real-time aerial monitoring is active for this project.
4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1687.81 Cr and is currently ongoing with physical progress at 25.8%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
8,212 frames · NHAI surveillance footage · UPC N/05005/08004/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bel"?
- Current physical progress: 25.8%. Financial progress: 24.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 10-03-2026. Likely completion: 30-03-2028.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is Ram Kripal Singh Construction Pvt. Ltd. The project is under RO-Patna and covers 42.21 km on 119D.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1687.81 Crore. Total capital cost: ₹2185.75 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/05005/08004/BR in NHAI?
- UPC (Unique Project Code) N/05005/08004/BR refers to "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.