All NHAI Projects
119DHAM 4916 Drone Frames

4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D

UPC: N/05005/08004/BR

Physical Progress

30.4%

Drone-monitored

Financial Progress

30.3%

Of awarded cost

Awarded Cost

₹1688 Cr

Contract value

Length

42.21 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4916

Aerial captures

Project Progress

Physical Progress30.4%
Financial Progress30.3%

Stage

Under Construction (AD issued)

Due Date

10-03-2026

Likely Date

30-03-2028

Completion

30.4%

Physical Done

DoneRemaining

Project Timeline

Awarded

11-03-2024

Construction Started

11-03-2024

In Progress

Near Completion

-

Completed

30-03-2028

Physical vs Financial Progress

Project Details

UPC

N/05005/08004/BR

National Highway

119D

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

42.21 km

Contractor

Ram Kripal Singh Construction Pvt. Ltd

Project Stage

Under Construction (AD issued)

Drone Frames

4916 frames

Last Flight

2026-07-27

Cost & Timeline

Awarded Cost

₹1687.81 Cr

Capital Cost

₹2185.75 Cr

Start Date

11-03-2024

PCOD Date

-

Scheduled Completion

10-03-2026

Likely Completion

30-03-2028

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:38:39

Contractor Profile

Ram Kripal Singh Construction Pvt. Ltd

RO-Patna119DHAM

Project Intelligence

1

Physical progress stands at 30.4%. Financial utilization at 30.3%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 42.21 km on 119D, improving regional connectivity.

4

4916 drone frames uploaded — real-time aerial monitoring is active for this project.

4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1687.81 Cr and is currently ongoing with physical progress at 30.4%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

4,916 frames · NHAI surveillance footage · UPC N/05005/08004/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bel"?
Current physical progress: 30.4%. Financial progress: 30.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 10-03-2026. Likely completion: 30-03-2028.
QWho is the contractor for this NHAI highway project?
The contractor for 4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D is Ram Kripal Singh Construction Pvt. Ltd. The project is under RO-Patna and covers 42.21 km on 119D.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1687.81 Crore. Total capital cost: ₹2185.75 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/05005/08004/BR in NHAI?
UPC (Unique Project Code) N/05005/08004/BR refers to "4L of Greenfield Alignment from Km. 47.000 to Km. 89.210 of Balbhadarpur to Bela Nawda Section of NH-119D" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.