Physical Progress
25.8%
Drone-monitored
Financial Progress
24.3%
Of awarded cost
Awarded Cost
₹1688 Cr
Contract value
Length
42.21 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
8212
Aerial captures
Stage
Under Construction (AD issued)
Due Date
10-03-2026
Likely Date
30-03-2028
25.8%
Physical Done
Awarded
11-03-2024
Construction Started
11-03-2024
In Progress
Near Completion
-
Completed
30-03-2028
UPC
N/05005/08004/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
42.21 km
Contractor
Ram Kripal Singh Construction Pvt. Ltd
Project Stage
Under Construction (AD issued)
Drone Frames
8212 frames
Last Flight
2026-02-24
Awarded Cost
₹1687.81 Cr
Capital Cost
₹2185.75 Cr
Start Date
11-03-2024
PCOD Date
-
Scheduled Completion
10-03-2026
Likely Completion
30-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 10:01:05
Ram Kripal Singh Construction Pvt. Ltd
Physical progress stands at 25.8%. Financial utilization at 24.3%.
Project is on schedule or ahead of planned completion date.
Covers 42.21 km on 119D, improving regional connectivity.
8212 drone frames uploaded — real-time aerial monitoring is active for this project.
8,212 frames · NHAI surveillance footage · UPC N/05005/08004/BR