Physical Progress
32.7%
Drone-monitored
Financial Progress
31.3%
Of awarded cost
Awarded Cost
₹1358 Cr
Contract value
Length
47 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4382
Aerial captures
Stage
Under Construction (AD issued)
Due Date
15-02-2025
Likely Date
30-03-2028
32.7%
Physical Done
Awarded
16-02-2023
Construction Started
16-02-2023
In Progress
Near Completion
-
Completed
30-03-2028
UPC
N/05005/08003/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
47 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4382 frames
Last Flight
2026-05-27
Awarded Cost
₹1358.00 Cr
Capital Cost
₹1857.58 Cr
Start Date
16-02-2023
PCOD Date
-
Scheduled Completion
15-02-2025
Likely Completion
30-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 09:47:54
Megha Engineering and Infrastructure Ltd.
Physical progress stands at 32.7%. Financial utilization at 31.3%.
Project is on schedule or ahead of planned completion date.
Covers 47 km on 119D, improving regional connectivity.
4382 drone frames uploaded — real-time aerial monitoring is active for this project.
4,382 frames · NHAI surveillance footage · UPC N/05005/08003/BR