4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)
Physical Progress
32.7%
Drone-monitored
Financial Progress
31.3%
Of awarded cost
Awarded Cost
₹1358 Cr
Contract value
Length
47 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
4382
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
15-02-2025
Likely Date
30-03-2028
Completion
32.7%
Physical Done
Project Timeline
Awarded
16-02-2023
Construction Started
16-02-2023
In Progress
Near Completion
-
Completed
30-03-2028
Physical vs Financial Progress
Project Details
UPC
N/05005/08003/BR
National Highway
119D
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
47 km
Contractor
Megha Engineering and Infrastructure Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
4382 frames
Last Flight
2026-05-27
Cost & Timeline
Awarded Cost
₹1358.00 Cr
Capital Cost
₹1857.58 Cr
Start Date
16-02-2023
PCOD Date
-
Scheduled Completion
15-02-2025
Likely Completion
30-03-2028
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-18 09:47:54
Contractor Profile
Megha Engineering and Infrastructure Ltd.
Project Intelligence
Physical progress stands at 32.7%. Financial utilization at 31.3%.
Project is on schedule or ahead of planned completion date.
Covers 47 km on 119D, improving regional connectivity.
4382 drone frames uploaded — real-time aerial monitoring is active for this project.
4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1358.00 Cr and is currently ongoing with physical progress at 32.7%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
4,382 frames · NHAI surveillance footage · UPC N/05005/08003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)"?
- Current physical progress: 32.7%. Financial progress: 31.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 15-02-2025. Likely completion: 30-03-2028.
- Who is the contractor for this NHAI highway project?
- The contractor for 4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 47 km on 119D.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1358.00 Crore. Total capital cost: ₹1857.58 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/05005/08003/BR in NHAI?
- UPC (Unique Project Code) N/05005/08003/BR refers to "4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.