Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
All NHAI Projects
119DHAM 4382 Drone Frames

4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)

UPC: N/05005/08003/BR

Physical Progress

32.7%

Drone-monitored

Financial Progress

31.3%

Of awarded cost

Awarded Cost

₹1358 Cr

Contract value

Length

47 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

4382

Aerial captures

Project Progress

Physical Progress32.7%
Financial Progress31.3%

Stage

Under Construction (AD issued)

Due Date

15-02-2025

Likely Date

30-03-2028

Completion

32.7%

Physical Done

DoneRemaining

Project Timeline

Awarded

16-02-2023

Construction Started

16-02-2023

In Progress

Near Completion

-

Completed

30-03-2028

Physical vs Financial Progress

Project Details

UPC

N/05005/08003/BR

National Highway

119D

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

47 km

Contractor

Megha Engineering and Infrastructure Ltd.

Project Stage

Under Construction (AD issued)

Drone Frames

4382 frames

Last Flight

2026-05-27

Cost & Timeline

Awarded Cost

₹1358.00 Cr

Capital Cost

₹1857.58 Cr

Start Date

16-02-2023

PCOD Date

-

Scheduled Completion

15-02-2025

Likely Completion

30-03-2028

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-06-18 09:47:54

Contractor Profile

Megha Engineering and Infrastructure Ltd.

RO-Patna119DHAM

Project Intelligence

1

Physical progress stands at 32.7%. Financial utilization at 31.3%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 47 km on 119D, improving regional connectivity.

4

4382 drone frames uploaded — real-time aerial monitoring is active for this project.

4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III) is a National Highways Authority of India (NHAI) project on 119D in Bihar. The project has an awarded cost of ₹1358.00 Cr and is currently ongoing with physical progress at 32.7%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

4,382 frames · NHAI surveillance footage · UPC N/05005/08003/BR

View Drone Images

Frequently Asked Questions

What is the current status of the NHAI project "4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)"?
Current physical progress: 32.7%. Financial progress: 31.3%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 15-02-2025. Likely completion: 30-03-2028.
Who is the contractor for this NHAI highway project?
The contractor for 4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III) is Megha Engineering and Infrastructure Ltd.. The project is under RO-Patna and covers 47 km on 119D.
What is the cost of this NHAI highway project?
The awarded cost is ₹1358.00 Crore. Total capital cost: ₹1857.58 Crore. The project is on 119D in Bihar, monitored via drone surveillance by NHAI.
What is UPC N/05005/08003/BR in NHAI?
UPC (Unique Project Code) N/05005/08003/BR refers to "4L Greenfield Alignment from Kalyanapur to Tal Dashraha of NH-119D (Pkg-III)" — a National Highway project on 119D in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.