Original Cost
₹359 Cr
Baseline estimate
Revised Cost
₹359 Cr
Latest approved cost
Expenditure
₹341 Cr
Spent to date
Utilization
95.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18 Cr
Budget left
Spent
₹341 Cr
Remaining
₹18 Cr
Total
₹359 Cr
Project Approved
Construction / Implementation
Original End Date
30/09/2023
Revised Completion
31/12/2025
Completed
Project is within original budget of ₹359 Cr — no cost escalation recorded.
Expenditure stands at ₹341 Cr, which is 95.1% of the revised project cost.
Remaining budget: ₹18 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.