Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan 8.1 GW under Phase II- Part- G1
Original Cost
₹359 Cr
Baseline estimate
Revised Cost
₹359 Cr
Latest approved cost
Expenditure
₹341 Cr
Spent to date
Utilization
95.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18 Cr
Budget left
Budget Utilization
95.1%Spent
₹341 Cr
Remaining
₹18 Cr
Total
₹359 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/09/2023
Revised Completion
31/12/2025
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹359 Cr — no cost escalation recorded.
Expenditure stands at ₹341 Cr, which is 95.1% of the revised project cost.
Remaining budget: ₹18 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan 8.1 GW under Phase II- Part- G1 is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. This work is part of the development of Delhi Solar Power — central government project titles use official ministry terminology rather than the common name. The original approved cost is ₹359.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission system strengthening scheme for evacuation of power from solar ener"?
- Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan 8.1 GW under Phase II- Part- G1 is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Delhi. Original cost: ₹359 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹359 Cr has not been significantly revised. Expenditure: ₹341 Cr (95.1% of cost). Data as of 2025-10.
- QWhich ministry is responsible for this project?
- Transmission system strengthening scheme for evacuation of p is under the Ministry of Power in the Transmission & Distribution sector. Project code: 608301. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission system strengthening scheme for evacuation of p is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.
- QIs this the Delhi Solar Power project?
- Yes — "Transmission system strengthening scheme for evacuation of power from solar energy zones in Rajasthan 8.1 GW under Phase II- Part- G1" is the official DPIIT/IPM project title covering Delhi Solar Power development works. Central government project titles use official ministry terminology rather than the site's common name.