Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
Industrial Units384+ Approved|
Awarded Value₹24,500+ Cr|
MP Fund Utilization78% Average|
Highway Network1,200 km+|
Energy Stability23.5 Hrs/Day|
Active Projects842 Tracked|
Education Index+15.3% Trend|
Cabinet decisionsActive Tracking|
Airport movements3.2M+ Annual|
EC MonitoringLive Updates|
Litigation tracker480+ Cases|
BiharInfraTalesBIHARINFRATALES
DashboardTenderCensusMP FundCabinetEC MonitoringAirportsTownshipsLitigation
  1. BiharInfraTales
  2. /IPM Dashboard
  3. /Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [
Transmission & DistributionIPM · Central Project#617181

Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [Section-II] and Barmer-I PS [POWERGRID Fatehgarh Barmer Augmentation Transmission Limited]

Ministry of PowerRajasthanData: 2026-05
Revised Cost: ₹404 CrUtilization: 7.0%

Original Cost

₹404 Cr

Baseline estimate

On Budget

Revised Cost

₹404 Cr

Latest approved cost

Expenditure

₹28 Cr

Spent to date

Utilization

7.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹376 Cr

Budget left

Budget Utilization

7.0%
0%25%50%75%100%

Spent

₹28 Cr

Remaining

₹376 Cr

Total

₹404 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

20/12/2026

Revised Completion

30/06/2027

Completed

Project Details

Project Code617181
SectorTransmission & Distribution
MinistryMinistry of Power
StateRajasthan
Data Month2026-05

Financial & Timeline

Original Cost₹404 Cr
Revised Cost₹404 Cr
Expenditure₹28 Cr
Original End Date20/12/2026
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹404 Cr — no cost escalation recorded.

Expenditure stands at ₹28 Cr, which is 7.0% of the revised project cost.

Remaining budget: ₹376 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Frequently Asked Questions

What is IPM project "Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [Section-II] and Barmer-I PS [P"?
Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [Section-II] and Barmer-I PS [POWERGRID Fatehgarh Barmer Augmentation Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Rajasthan. Original cost: ₹404 Cr.
What is the cost overrun for this Bihar IPM project?
The original cost of ₹404 Cr has not been significantly revised. Expenditure: ₹28 Cr (7.0% of cost). Data as of 2026-05.
Which ministry is responsible for this project?
Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [Section-II is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617181. Bihar is one of the states tracked under the central IPM dashboard for this project.
What is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Augmentation at Fatehgarh-II PS, Fatehgarh-IV PS [Section-II is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.

Related Resources

IPM

IPM Central Project Dashboard

All central infrastructure projects in Bihar

Projects

Bihar State Projects

State-funded infrastructure project tracker

NHAI

NHAI Drone Tracker

Real-time NHAI highway construction monitoring

Railway

Bihar Railway Projects

Railway infrastructure project tracker

RCD

Bihar RCD PMIS

State road and bridge project tracker

Tenders

Bihar Government Tenders

Procurement notices for infrastructure projects

Cabinet

Bihar Cabinet Decisions

Policy approvals for infrastructure

EC

EC & Forest Clearances

Environmental clearances for Bihar projects

Upcoming

Upcoming Bihar Projects

Infrastructure pipeline and future projects

Districts

Bihar District Data

District demographics and infrastructure overview