Augmentation of 1x1500 MVA 3rd 765/400 kV transformation capacity at Kurnool New Substation
Original Cost
₹164 Cr
Baseline estimate
Revised Cost
₹164 Cr
Latest approved cost
Expenditure
₹146 Cr
Spent to date
Utilization
88.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹18 Cr
Budget left
Budget Utilization
88.8%Spent
₹146 Cr
Remaining
₹18 Cr
Total
₹164 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
26/09/2025
Revised Completion
31/03/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹164 Cr — no cost escalation recorded.
Expenditure stands at ₹146 Cr, which is 88.8% of the revised project cost.
Remaining budget: ₹18 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Augmentation of 1x1500 MVA 3rd 765/400 kV transformation capacity at Kurnool New Substation is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹164.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Augmentation of 1x1500 MVA 3rd 765/400 kV transformation capacity at Kurnool Ne"?
- Augmentation of 1x1500 MVA 3rd 765/400 kV transformation capacity at Kurnool New Substation is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Andhra Pradesh. Original cost: ₹164 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹164 Cr has not been significantly revised. Expenditure: ₹146 Cr (88.8% of cost). Data as of 2026-02.
- QWhich ministry is responsible for this project?
- Augmentation of 1x1500 MVA 3rd 765/400 kV transformation ca is under the Ministry of Power in the Transmission & Distribution sector. Project code: 612856. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Augmentation of 1x1500 MVA 3rd 765/400 kV transformation ca is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.