Transmission & DistributionIPM · Central Project#619028

Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VSC HVDC Station in Kerala

Ministry of PowerKerala
Revised Cost: ₹173 CrUtilization: 1.2%

Original Cost

₹173 Cr

Baseline estimate

On budget

Revised Cost

₹173 Cr

Latest approved cost

Expenditure

₹2 Cr

Spent to date

Utilization

1.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹171 Cr

Budget left

Budget Utilization

1.2%
0%25%50%75%100%

Spent

₹2 Cr

Remaining

₹171 Cr

Total

₹173 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

21/08/2027

Revised Completion

31/12/2027

Completed

Project Details

Project Code619028
SectorTransmission & Distribution
MinistryMinistry of Power
StateKerala
Data Month2026-08

Financial Summary

Original Cost₹173 Cr
Revised Cost₹173 Cr
Expenditure₹2 Cr
Original End Date21/08/2027
Revised Date31/12/2027

Project Intelligence

Project is within original budget of ₹173 Cr — no cost escalation recorded.

Expenditure stands at ₹2 Cr, which is 1.2% of the revised project cost.

Remaining budget: ₹171 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VSC HVDC Station in Kerala is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹173.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VSC HVDC Station in Ke"?
Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VSC HVDC Station in Kerala is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Kerala. Original cost: ₹173 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹173 Cr has not been significantly revised. Expenditure: ₹2 Cr (1.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VS is under the Ministry of Power in the Transmission & Distribution sector. Project code: 619028. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Augmentation of 1x500 MVA 400/220kV ICT [3rd] at Thrissur VS is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.