Transmission & DistributionIPM · Central Project +33.1% overrun#608922

Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G

Ministry of PowerHaryana
Revised Cost: ₹2218 CrUtilization: 96.0%Overrun: +₹552 Cr

Original Cost

₹1666 Cr

Baseline estimate

+33% overrun

Revised Cost

₹2218 Cr

Latest approved cost

Expenditure

₹2129 Cr

Spent to date

Utilization

96.0%

Of revised budget

Escalated

Cost Status

+33.1%

+₹552 Cr increase

Remaining

₹89 Cr

Budget left

Budget Utilization

96.0%
0%25%50%75%100%

Spent

₹2129 Cr

Remaining

₹89 Cr

Total

₹2218 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1666 Cr

Revised Cost

₹2218 Cr

Increase

+₹552 Cr

Escalation

+33.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/11/2023

Revised Completion

30/11/2025

Completed

Project Details

Project Code608922
SectorTransmission & Distribution
MinistryMinistry of Power
StateHaryana
Data Month2025-10

Financial Summary

Original Cost₹1666 Cr
Revised Cost₹2218 Cr
Expenditure₹2129 Cr
Original End Date30/11/2023
Revised Date30/11/2025

Project Intelligence

Cost has increased by ₹552 Cr (33.1%) from the original estimate of ₹1666 Cr.

Expenditure stands at ₹2129 Cr, which is 96.0% of the revised project cost.

Remaining budget: ₹89 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹1666.00 Cr, later revised to ₹2218.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission System Strengthening Scheme for evacuation of power from SEZ in Raj"?
Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Haryana. Original cost: ₹1666 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1666 Cr and has been revised to ₹2218 Cr — a cost overrun of +33.1%. Expenditure to date: ₹2129 Cr (96.0% of revised cost). Data as of 2025-10.
QWhich ministry is responsible for this project?
Transmission System Strengthening Scheme for evacuation of p is under the Ministry of Power in the Transmission & Distribution sector. Project code: 608922. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System Strengthening Scheme for evacuation of p is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.