Original Cost
₹1666 Cr
Baseline estimate
Revised Cost
₹2218 Cr
Latest approved cost
Expenditure
₹2129 Cr
Spent to date
Utilization
96.0%
Of revised budget
Cost Status
+33.1%
+₹552 Cr increase
Remaining
₹89 Cr
Budget left
Spent
₹2129 Cr
Remaining
₹89 Cr
Total
₹2218 Cr
Original Cost
₹1666 Cr
Revised Cost
₹2218 Cr
Increase
+₹552 Cr
Escalation
+33.1%
Project Approved
Construction / Implementation
Original End Date
30/11/2023
Revised Completion
30/11/2025
Completed
Cost has increased by ₹552 Cr (33.1%) from the original estimate of ₹1666 Cr.
Expenditure stands at ₹2129 Cr, which is 96.0% of the revised project cost.
Remaining budget: ₹89 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.