Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G
Original Cost
₹1666 Cr
Baseline estimate
Revised Cost
₹2218 Cr
Latest approved cost
Expenditure
₹2129 Cr
Spent to date
Utilization
96.0%
Of revised budget
Cost Status
+33.1%
+₹552 Cr increase
Remaining
₹89 Cr
Budget left
Budget Utilization
96.0%Spent
₹2129 Cr
Remaining
₹89 Cr
Total
₹2218 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1666 Cr
Revised Cost
₹2218 Cr
Increase
+₹552 Cr
Escalation
+33.1%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
30/11/2023
Revised Completion
30/11/2025
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹552 Cr (33.1%) from the original estimate of ₹1666 Cr.
Expenditure stands at ₹2129 Cr, which is 96.0% of the revised project cost.
Remaining budget: ₹89 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.
Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹1666.00 Cr, later revised to ₹2218.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Transmission System Strengthening Scheme for evacuation of power from SEZ in Raj"?
- Transmission System Strengthening Scheme for evacuation of power from SEZ in Rajasthan 8.1 GW under Phase II Part G is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Haryana. Original cost: ₹1666 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1666 Cr and has been revised to ₹2218 Cr — a cost overrun of +33.1%. Expenditure to date: ₹2129 Cr (96.0% of revised cost). Data as of 2025-10.
- QWhich ministry is responsible for this project?
- Transmission System Strengthening Scheme for evacuation of p is under the Ministry of Power in the Transmission & Distribution sector. Project code: 608922. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission System Strengthening Scheme for evacuation of p is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.