Original Cost
₹428 Cr
Baseline estimate
Revised Cost
₹428 Cr
Latest approved cost
Expenditure
₹415 Cr
Spent to date
Utilization
97.1%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹13 Cr
Budget left
Spent
₹415 Cr
Remaining
₹13 Cr
Total
₹428 Cr
Project Approved
Construction / Implementation
Original End Date
15/06/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹428 Cr — no cost escalation recorded.
Expenditure stands at ₹415 Cr, which is 97.1% of the revised project cost.
Remaining budget: ₹13 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.