Original Cost
₹2191 Cr
Baseline estimate
Revised Cost
₹2191 Cr
Latest approved cost
Expenditure
₹2139 Cr
Spent to date
Utilization
97.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹52 Cr
Budget left
Spent
₹2139 Cr
Remaining
₹52 Cr
Total
₹2191 Cr
Project Approved
Construction / Implementation
Original End Date
30/04/2025
Revised Completion
28/02/2026
Completed
Project is within original budget of ₹2191 Cr — no cost escalation recorded.
Expenditure stands at ₹2139 Cr, which is 97.6% of the revised project cost.
Remaining budget: ₹52 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.