Transmission & DistributionIPM · Central Project#615339

Transmission system for evacuation of power from Rajasthan REZ Ph-IV [Part-3/6GW] [Bikaner complex] Part A [SPV Name POWERGRID Bikaner IV Transmission Limited]

Ministry of PowerRajasthan
Revised Cost: ₹5969 CrUtilization: 38.0%

Original Cost

₹5969 Cr

Baseline estimate

On budget

Revised Cost

₹5969 Cr

Latest approved cost

Expenditure

₹2268 Cr

Spent to date

Utilization

38.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹3701 Cr

Budget left

Budget Utilization

38.0%
0%25%50%75%100%

Spent

₹2268 Cr

Remaining

₹3701 Cr

Total

₹5969 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

11/11/2026

Revised Completion

30/04/2027

Completed

Project Details

Project Code615339
SectorTransmission & Distribution
MinistryMinistry of Power
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹5969 Cr
Revised Cost₹5969 Cr
Expenditure₹2268 Cr
Original End Date11/11/2026
Revised Date30/04/2027

Project Intelligence

Project is within original budget of ₹5969 Cr — no cost escalation recorded.

Expenditure stands at ₹2268 Cr, which is 38.0% of the revised project cost.

Remaining budget: ₹3701 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission system for evacuation of power from Rajasthan REZ Ph-IV [Part-3/6GW] [Bikaner complex] Part A [SPV Name POWERGRID Bikaner IV Transmission Limited] is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹5969.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission system for evacuation of power from Rajasthan REZ Ph-IV [Part-3/6GW"?
Transmission system for evacuation of power from Rajasthan REZ Ph-IV [Part-3/6GW] [Bikaner complex] Part A [SPV Name POWERGRID Bikaner IV Transmission Limited] is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Rajasthan. Original cost: ₹5969 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹5969 Cr has not been significantly revised. Expenditure: ₹2268 Cr (38.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission system for evacuation of power from Rajasthan R is under the Ministry of Power in the Transmission & Distribution sector. Project code: 615339. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission system for evacuation of power from Rajasthan R is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.