Transmission & DistributionIPM · Central Project#617179

Transmission Scheme for evacuation of Power from Ratle HEP [850 MW] & kiru [624 MW] Part B

Ministry of PowerJammu & Kashmir
Revised Cost: ₹219 CrUtilization: 1.7%

Original Cost

₹219 Cr

Baseline estimate

On budget

Revised Cost

₹219 Cr

Latest approved cost

Expenditure

₹4 Cr

Spent to date

Utilization

1.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹215 Cr

Budget left

Budget Utilization

1.7%
0%25%50%75%100%

Spent

₹4 Cr

Remaining

₹215 Cr

Total

₹219 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/07/2026

Revised Completion

30/06/2027

Completed

Project Details

Project Code617179
SectorTransmission & Distribution
MinistryMinistry of Power
StateJammu & Kashmir
Data Month2026-08

Financial Summary

Original Cost₹219 Cr
Revised Cost₹219 Cr
Expenditure₹4 Cr
Original End Date14/07/2026
Revised Date30/06/2027

Project Intelligence

Project is within original budget of ₹219 Cr — no cost escalation recorded.

Expenditure stands at ₹4 Cr, which is 1.7% of the revised project cost.

Remaining budget: ₹215 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Transmission Scheme for evacuation of Power from Ratle HEP [850 MW] & kiru [624 MW] Part B is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹219.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Transmission Scheme for evacuation of Power from Ratle HEP [850 MW] & kiru [624 "?
Transmission Scheme for evacuation of Power from Ratle HEP [850 MW] & kiru [624 MW] Part B is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Jammu & Kashmir. Original cost: ₹219 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹219 Cr has not been significantly revised. Expenditure: ₹4 Cr (1.7% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Transmission Scheme for evacuation of Power from Ratle HEP [ is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617179. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Transmission Scheme for evacuation of Power from Ratle HEP [ is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.