Original Cost
₹1168 Cr
Baseline estimate
Revised Cost
₹1167 Cr
Latest approved cost
Expenditure
₹1148 Cr
Spent to date
Utilization
98.3%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹19 Cr
Budget left
Spent
₹1148 Cr
Remaining
₹19 Cr
Total
₹1167 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
30/11/2025
Completed
Project is within original budget of ₹1168 Cr — no cost escalation recorded.
Expenditure stands at ₹1148 Cr, which is 98.3% of the revised project cost.
Remaining budget: ₹19 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.