Original Cost
₹25.0K Cr
Baseline estimate
Revised Cost
₹25.0K Cr
Latest approved cost
Expenditure
₹426 Cr
Spent to date
Utilization
1.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹24.6K Cr
Budget left
Spent
₹426 Cr
Remaining
₹24.6K Cr
Total
₹25.0K Cr
Project Approved
Construction / Implementation
Original End Date
20/07/2029
Revised Completion
Completed
Mega infrastructure project worth ₹25.0K Cr — among the largest central projects in Rajasthan.
Project is within original budget of ₹25.0K Cr — no cost escalation recorded.
Expenditure stands at ₹426 Cr, which is 1.7% of the revised project cost.
Remaining budget: ₹24.6K Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.