Transmission & DistributionIPM · Central Project#617405

Jamnagar Transmission Limited

Ministry of PowerGujarat
Revised Cost: ₹4000 CrUtilization: 17.4%

Original Cost

₹4000 Cr

Baseline estimate

On budget

Revised Cost

₹4000 Cr

Latest approved cost

Expenditure

₹698 Cr

Spent to date

Utilization

17.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹3302 Cr

Budget left

Budget Utilization

17.4%
0%25%50%75%100%

Spent

₹698 Cr

Remaining

₹3302 Cr

Total

₹4000 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

14/10/2026

Revised Completion

30/09/2027

Completed

Project Details

Project Code617405
SectorTransmission & Distribution
MinistryMinistry of Power
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹4000 Cr
Revised Cost₹4000 Cr
Expenditure₹698 Cr
Original End Date14/10/2026
Revised Date30/09/2027

Project Intelligence

Project is within original budget of ₹4000 Cr — no cost escalation recorded.

Expenditure stands at ₹698 Cr, which is 17.4% of the revised project cost.

Remaining budget: ₹3302 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Transmission & Distribution. Ministry: Ministry of Power.

Jamnagar Transmission Limited is a centrally-funded infrastructure project under Ministry of Power, in the Transmission & Distribution sector. The original approved cost is ₹4000.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Jamnagar Transmission Limited"?
Jamnagar Transmission Limited is a centrally-funded infrastructure project under the Ministry of Power, tracked through the Investment Project Monitoring (IPM) system. Sector: Transmission & Distribution. State: Gujarat. Original cost: ₹4000 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹4000 Cr has not been significantly revised. Expenditure: ₹698 Cr (17.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Jamnagar Transmission Limited is under the Ministry of Power in the Transmission & Distribution sector. Project code: 617405. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Jamnagar Transmission Limited is one of several Bihar projects tracked under the Transmission & Distribution sector on the IPM system.