Original Cost
₹4000 Cr
Baseline estimate
Revised Cost
₹4000 Cr
Latest approved cost
Expenditure
₹553 Cr
Spent to date
Utilization
13.8%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹3447 Cr
Budget left
Spent
₹553 Cr
Remaining
₹3447 Cr
Total
₹4000 Cr
Project Approved
Construction / Implementation
Original End Date
14/10/2026
Revised Completion
Completed
Project is within original budget of ₹4000 Cr — no cost escalation recorded.
Expenditure stands at ₹553 Cr, which is 13.8% of the revised project cost.
Remaining budget: ₹3447 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Transmission & Distribution. Ministry: Ministry of Power.