6L Greenfield Varanasi-Ranchi-Kolkata Highway from Pachmon village to Anarbansalea village (From KM. 116+000 to KM. 151+200) (Package-6)
Physical Progress
20.2%
Drone-monitored
Financial Progress
12.0%
Of awarded cost
Awarded Cost
₹1260 Cr
Contract value
Length
35.2 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2603
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
03-09-2027
Likely Date
03-09-2027
Completion
20.2%
Physical Done
Project Timeline
Awarded
04-09-2025
Construction Started
04-09-2025
In Progress
Near Completion
-
Completed
03-09-2027
Physical vs Financial Progress
Project Details
UPC
N/04044/01002/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
35.2 km
Contractor
Varanasi Kolkata Highway Package 6 PVT LTD
Project Stage
Under Construction (AD issued)
Drone Frames
2603 frames
Last Flight
2026-02-22
Cost & Timeline
Awarded Cost
₹1260.00 Cr
Capital Cost
₹1915.99 Cr
Start Date
04-09-2025
PCOD Date
-
Scheduled Completion
03-09-2027
Likely Completion
03-09-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-16 09:06:53
Contractor Profile
Varanasi Kolkata Highway Package 6 PVT LTD
Project Intelligence
Physical progress stands at 20.2%. Financial utilization at 12.0%.
Project is on schedule or ahead of planned completion date.
Covers 35.2 km on 319B, improving regional connectivity.
2603 drone frames uploaded — real-time aerial monitoring is active for this project.
6L Greenfield Varanasi-Ranchi-Kolkata Highway from Pachmon village to Anarbansalea village (From KM. 116+000 to KM. 151+200) (Package-6) is a National Highways Authority of India (NHAI) project on 319B in Bihar. The project has an awarded cost of ₹1260.00 Cr and is currently **ongoing** with physical progress at 20.2%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,603 frames · NHAI surveillance footage · UPC N/04044/01002/BR
Frequently Asked Questions
- What is the current status of the NHAI project "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Pachmon village to Anarbansal"?
- Current physical progress: 20.2%. Financial progress: 12.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 03-09-2027. Likely completion: 03-09-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for 6L Greenfield Varanasi-Ranchi-Kolkata Highway from Pachmon village to Anarbansalea village (From KM. 116+000 to KM. 151+200) (Package-6) is Varanasi Kolkata Highway Package 6 PVT LTD. The project is under RO-Patna and covers 35.2 km on 319B.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1260.00 Crore. Total capital cost: ₹1915.99 Crore. The project is on 319B in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/04044/01002/BR in NHAI?
- UPC (Unique Project Code) N/04044/01002/BR refers to "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Pachmon village to Anarbansalea village (From KM. 116+000 to KM. 151+200) (Package-6)" — a National Highway project on 319B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.