Physical Progress
20.1%
Drone-monitored
Financial Progress
20.1%
Of awarded cost
Awarded Cost
₹1113 Cr
Contract value
Length
36 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
1982
Aerial captures
Stage
Under Construction (AD issued)
Due Date
05-10-2027
Likely Date
05-10-2027
20.1%
Physical Done
Awarded
06-10-2025
Construction Started
06-10-2025
In Progress
Near Completion
-
Completed
05-10-2027
UPC
N/04044/01004/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
36 km
Contractor
PNC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
1982 frames
Last Flight
2026-01-25
Awarded Cost
₹1113.43 Cr
Capital Cost
₹1576.94 Cr
Start Date
06-10-2025
PCOD Date
-
Scheduled Completion
05-10-2027
Likely Completion
05-10-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 17:51:41
PNC Infratech Pvt. Ltd.
Physical progress stands at 20.1%. Financial utilization at 20.1%.
Project is on schedule or ahead of planned completion date.
Covers 36 km on 319B, improving regional connectivity.
1982 drone frames uploaded — real-time aerial monitoring is active for this project.
1,982 frames · NHAI surveillance footage · UPC N/04044/01004/BR