Physical Progress
21.2%
Drone-monitored
Financial Progress
21.2%
Of awarded cost
Awarded Cost
₹891 Cr
Contract value
Length
27 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2566
Aerial captures
Stage
Under Construction (AD issued)
Due Date
05-10-2027
Likely Date
05-10-2027
21.2%
Physical Done
Awarded
06-10-2025
Construction Started
06-10-2025
In Progress
Near Completion
-
Completed
05-10-2027
UPC
N/04044/01003/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
27 km
Contractor
PNC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
2566 frames
Last Flight
2025-09-28
Awarded Cost
₹891.00 Cr
Capital Cost
₹1240.93 Cr
Start Date
06-10-2025
PCOD Date
-
Scheduled Completion
05-10-2027
Likely Completion
05-10-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 15:25:26
PNC Infratech Pvt. Ltd.
Physical progress stands at 21.2%. Financial utilization at 21.2%.
Project is on schedule or ahead of planned completion date.
Covers 27 km on 319B, improving regional connectivity.
2566 drone frames uploaded — real-time aerial monitoring is active for this project.
2,566 frames · NHAI surveillance footage · UPC N/04044/01003/BR