6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with Chandauli-Chainpur Road near Khainti village to junction with Bhabhua-Adhaura road near Palka village (from Km. 27.000 to Km. 54.000) (Pkg-2)
Physical Progress
21.2%
Drone-monitored
Financial Progress
21.2%
Of awarded cost
Awarded Cost
₹891 Cr
Contract value
Length
27 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2566
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
05-10-2027
Likely Date
05-10-2027
Completion
21.2%
Physical Done
Project Timeline
Awarded
06-10-2025
Construction Started
06-10-2025
In Progress
Near Completion
-
Completed
05-10-2027
Physical vs Financial Progress
Project Details
UPC
N/04044/01003/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
27 km
Contractor
PNC Infratech Pvt. Ltd.
Project Stage
Under Construction (AD issued)
Drone Frames
2566 frames
Last Flight
2025-09-28
Cost & Timeline
Awarded Cost
₹891.00 Cr
Capital Cost
₹1240.93 Cr
Start Date
06-10-2025
PCOD Date
-
Scheduled Completion
05-10-2027
Likely Completion
05-10-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 15:25:26
Contractor Profile
PNC Infratech Pvt. Ltd.
Project Intelligence
Physical progress stands at 21.2%. Financial utilization at 21.2%.
Project is on schedule or ahead of planned completion date.
Covers 27 km on 319B, improving regional connectivity.
2566 drone frames uploaded — real-time aerial monitoring is active for this project.
6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with Chandauli-Chainpur Road near Khainti village to junction with Bhabhua-Adhaura road near Palka village (from Km. 27.000 to Km. 54.000) (Pkg-2) is a National Highways Authority of India (NHAI) project on 319B in Bihar. The project has an awarded cost of ₹891.00 Cr and is currently **ongoing** with physical progress at 21.2%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,566 frames · NHAI surveillance footage · UPC N/04044/01003/BR
Frequently Asked Questions
- What is the current status of the NHAI project "6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with Chandauli-Chain"?
- Current physical progress: 21.2%. Financial progress: 21.2%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 05-10-2027. Likely completion: 05-10-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for 6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with Chandauli-Chainpur Road near Khainti village to junction with Bhabhua-Adhaura road near Palka village (from Km. 27.000 to Km. 54.000) (Pkg-2) is PNC Infratech Pvt. Ltd.. The project is under RO-Patna and covers 27 km on 319B.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹891.00 Crore. Total capital cost: ₹1240.93 Crore. The project is on 319B in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/04044/01003/BR in NHAI?
- UPC (Unique Project Code) N/04044/01003/BR refers to "6L Greenfield Varanasi-Ranchi-Kolkata Highway from junction with Chandauli-Chainpur Road near Khainti village to junction with Bhabhua-Adhaura road near Palka village (from Km. 27.000 to Km. 54.000) (Pkg-2)" — a National Highway project on 319B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.