Physical Progress
22.3%
Drone-monitored
Financial Progress
8.0%
Of awarded cost
Awarded Cost
₹1248 Cr
Contract value
Length
33.5 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2426
Aerial captures
Stage
Under Construction (AD issued)
Due Date
30-06-2027
Likely Date
30-06-2027
22.3%
Physical Done
Awarded
01-07-2025
Construction Started
01-07-2025
In Progress
Near Completion
-
Completed
30-06-2027
UPC
N/04044/01001/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
33.5 km
Contractor
GR Varanasi Kolkata Highway Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
2426 frames
Last Flight
2025-08-28
Awarded Cost
₹1248.37 Cr
Capital Cost
₹1719.20 Cr
Start Date
01-07-2025
PCOD Date
-
Scheduled Completion
30-06-2027
Likely Completion
30-06-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 12:10:01
GR Varanasi Kolkata Highway Private Limited
Physical progress stands at 22.3%. Financial utilization at 8.0%.
Project is on schedule or ahead of planned completion date.
Covers 33.5 km on 319B, improving regional connectivity.
2426 drone frames uploaded — real-time aerial monitoring is active for this project.
2,426 frames · NHAI surveillance footage · UPC N/04044/01001/BR