6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7)

UPC: N/04044/01001/BR

Physical Progress

28.2%

Drone-monitored

Financial Progress

27.1%

Of awarded cost

Awarded Cost

₹1248 Cr

Contract value

Length

33.5 km

Road stretch

Schedule

On Track

On schedule

Drone Frames

2426

Aerial captures

Project Progress

Physical Progress28.2%
Financial Progress27.1%

Stage

Under Construction (AD issued)

Due Date

30-06-2027

Likely Date

10-03-2028

Completion

28.2%

Physical Done

DoneRemaining

Project Timeline

Awarded

01-07-2025

Construction Started

01-07-2025

In Progress

Near Completion

-

Completed

10-03-2028

Physical vs Financial Progress

Project Details

UPC

N/04044/01001/BR

National Highway

319B

Regional Office

RO-Patna

State

Bihar

Mode

HAM

Length

33.5 km

Contractor

GR Varanasi Kolkata Highway Private Limited

Project Stage

Under Construction (AD issued)

Drone Frames

2426 frames

Last Flight

2025-08-28

Cost & Timeline

Awarded Cost

₹1248.37 Cr

Capital Cost

₹1719.20 Cr

Start Date

01-07-2025

PCOD Date

-

Scheduled Completion

30-06-2027

Likely Completion

10-03-2028

Schedule Status

On schedule

Slippage Days

N/A

Data Updated

2026-09-20 21:37:16

Contractor Profile

GR Varanasi Kolkata Highway Private Limited

RO-Patna319BHAM

Project Intelligence

1

Physical progress stands at 28.2%. Financial utilization at 27.1%.

2

Project is on schedule or ahead of planned completion date.

3

Covers 33.5 km on 319B, improving regional connectivity.

4

2426 drone frames uploaded — real-time aerial monitoring is active for this project.

6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7) is a National Highways Authority of India (NHAI) project on 319B in Bihar. The project has an awarded cost of ₹1248.37 Cr and is currently ongoing with physical progress at 28.2%.

NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.

Drone Imagery Available

2,426 frames · NHAI surveillance footage · UPC N/04044/01001/BR

View Drone Images
?

Frequently Asked Questions

QWhat is the current status of the NHAI project "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagr"?
Current physical progress: 28.2%. Financial progress: 27.1%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-06-2027. Likely completion: 10-03-2028.
QWho is the contractor for this NHAI highway project?
The contractor for 6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7) is GR Varanasi Kolkata Highway Private Limited. The project is under RO-Patna and covers 33.5 km on 319B.
QWhat is the cost of this NHAI highway project?
The awarded cost is ₹1248.37 Crore. Total capital cost: ₹1719.20 Crore. The project is on 319B in Bihar, monitored via drone surveillance by NHAI.
QWhat is UPC N/04044/01001/BR in NHAI?
UPC (Unique Project Code) N/04044/01001/BR refers to "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7)" — a National Highway project on 319B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.