6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7)
Physical Progress
22.3%
Drone-monitored
Financial Progress
8.0%
Of awarded cost
Awarded Cost
₹1248 Cr
Contract value
Length
33.5 km
Road stretch
Schedule
On Track
On schedule
Drone Frames
2426
Aerial captures
Project Progress
Stage
Under Construction (AD issued)
Due Date
30-06-2027
Likely Date
30-06-2027
Completion
22.3%
Physical Done
Project Timeline
Awarded
01-07-2025
Construction Started
01-07-2025
In Progress
Near Completion
-
Completed
30-06-2027
Physical vs Financial Progress
Project Details
UPC
N/04044/01001/BR
National Highway
319B
Regional Office
RO-Patna
State
Bihar
Mode
HAM
Length
33.5 km
Contractor
GR Varanasi Kolkata Highway Private Limited
Project Stage
Under Construction (AD issued)
Drone Frames
2426 frames
Last Flight
2025-08-28
Cost & Timeline
Awarded Cost
₹1248.37 Cr
Capital Cost
₹1719.20 Cr
Start Date
01-07-2025
PCOD Date
-
Scheduled Completion
30-06-2027
Likely Completion
30-06-2027
Schedule Status
On schedule
Slippage Days
N/A
Data Updated
2026-06-17 12:10:01
Contractor Profile
GR Varanasi Kolkata Highway Private Limited
Project Intelligence
Physical progress stands at 22.3%. Financial utilization at 8.0%.
Project is on schedule or ahead of planned completion date.
Covers 33.5 km on 319B, improving regional connectivity.
2426 drone frames uploaded — real-time aerial monitoring is active for this project.
6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7) is a National Highways Authority of India (NHAI) project on 319B in Bihar. The project has an awarded cost of ₹1248.37 Cr and is currently **ongoing** with physical progress at 22.3%.
NHAI tracks physical progress on this project through periodic drone surveys, providing an independent view of on-ground construction status. Other projects on the same highway are listed below.
Drone Imagery Available
2,426 frames · NHAI surveillance footage · UPC N/04044/01001/BR
Frequently Asked Questions
- What is the current status of the NHAI project "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagr"?
- Current physical progress: 22.3%. Financial progress: 8.0%. Project stage: Under Construction (AD issued). On schedule. Scheduled completion: 30-06-2027. Likely completion: 30-06-2027.
- Who is the contractor for this NHAI highway project?
- The contractor for 6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7) is GR Varanasi Kolkata Highway Private Limited. The project is under RO-Patna and covers 33.5 km on 319B.
- What is the cost of this NHAI highway project?
- The awarded cost is ₹1248.37 Crore. Total capital cost: ₹1719.20 Crore. The project is on 319B in Bihar, monitored via drone surveillance by NHAI.
- What is UPC N/04044/01001/BR in NHAI?
- UPC (Unique Project Code) N/04044/01001/BR refers to "6L Greenfield Varanasi-Ranchi-Kolkata Highway from Anarbansalea village to Sagrampur village (From KM. 151+200 to KM. 184+700)(Package-7)" — a National Highway project on 319B in Bihar. NHAI uses UPCs to track drone monitoring progress and physical completion of highway construction.