Original Cost
₹483 Cr
Baseline estimate
Revised Cost
₹483 Cr
Latest approved cost
Expenditure
₹446 Cr
Spent to date
Utilization
92.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹37 Cr
Budget left
Spent
₹446 Cr
Remaining
₹37 Cr
Total
₹483 Cr
Project Approved
Construction / Implementation
Original End Date
31/05/2025
Revised Completion
30/06/2026
Completed
Project is within original budget of ₹483 Cr — no cost escalation recorded.
Expenditure stands at ₹446 Cr, which is 92.4% of the revised project cost.
Remaining budget: ₹37 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Mines.