Metals & MiningIPM · Central Project#709831

SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK MINING LEASE OF PANCHPATMAILI MINES

Ministry of MinesOdisha
Revised Cost: ₹483 CrUtilization: 94.4%

Original Cost

₹483 Cr

Baseline estimate

On budget

Revised Cost

₹483 Cr

Latest approved cost

Expenditure

₹456 Cr

Spent to date

Utilization

94.4%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹27 Cr

Budget left

Budget Utilization

94.4%
0%25%50%75%100%

Spent

₹456 Cr

Remaining

₹27 Cr

Total

₹483 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/05/2025

Revised Completion

30/06/2026

Completed

Project Details

Project Code709831
SectorMetals & Mining
MinistryMinistry of Mines
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹483 Cr
Revised Cost₹483 Cr
Expenditure₹456 Cr
Original End Date31/05/2025
Revised Date30/06/2026

Project Intelligence

Project is within original budget of ₹483 Cr — no cost escalation recorded.

Expenditure stands at ₹456 Cr, which is 94.4% of the revised project cost.

Remaining budget: ₹27 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Metals & Mining. Ministry: Ministry of Mines.

SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK MINING LEASE OF PANCHPATMAILI MINES is a centrally-funded infrastructure project under Ministry of Mines, in the Metals & Mining sector. The original approved cost is ₹483.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK"?
SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFINERY FROM SOUTH BLOCK MINING LEASE OF PANCHPATMAILI MINES is a centrally-funded infrastructure project under the Ministry of Mines, tracked through the Investment Project Monitoring (IPM) system. Sector: Metals & Mining. State: Odisha. Original cost: ₹483 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹483 Cr has not been significantly revised. Expenditure: ₹456 Cr (94.4% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFIN is under the Ministry of Mines in the Metals & Mining sector. Project code: 709831. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. SOURCING OF BAUXITE ARRANGEMENT FOR 5TH STREAM ALUMINA REFIN is one of several Bihar projects tracked under the Metals & Mining sector on the IPM system.