Capacity expansion of Deposit-14 and 14 NMZ at Kirandul
Original Cost
₹1700 Cr
Baseline estimate
Revised Cost
₹1756 Cr
Latest approved cost
Expenditure
₹303 Cr
Spent to date
Utilization
17.3%
Of revised budget
Cost Status
+3.3%
+₹56 Cr increase
Remaining
₹1453 Cr
Budget left
Budget Utilization
17.3%Spent
₹303 Cr
Remaining
₹1453 Cr
Total
₹1756 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1700 Cr
Revised Cost
₹1756 Cr
Increase
+₹56 Cr
Escalation
+3.3%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2028
Revised Completion
27/03/2028
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹56 Cr (3.3%) from the original estimate of ₹1700 Cr.
Expenditure stands at ₹303 Cr, which is 17.3% of the revised project cost.
Remaining budget: ₹1453 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Steel.
Capacity expansion of Deposit-14 and 14 NMZ at Kirandul is a centrally-funded infrastructure project under Ministry of Steel, in the Metals & Mining sector. The original approved cost is ₹1700.00 Cr, later revised to ₹1756.20 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Capacity expansion of Deposit-14 and 14 NMZ at Kirandul"?
- Capacity expansion of Deposit-14 and 14 NMZ at Kirandul is a centrally-funded infrastructure project under the Ministry of Steel, tracked through the Investment Project Monitoring (IPM) system. Sector: Metals & Mining. State: Chhattisgarh. Original cost: ₹1700 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1700 Cr and has been revised to ₹1756 Cr — a cost overrun of +3.3%. Expenditure to date: ₹303 Cr (17.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Capacity expansion of Deposit-14 and 14 NMZ at Kirandul is under the Ministry of Steel in the Metals & Mining sector. Project code: 615202. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Capacity expansion of Deposit-14 and 14 NMZ at Kirandul is one of several Bihar projects tracked under the Metals & Mining sector on the IPM system.