Original Cost
₹1856 Cr
Baseline estimate
Revised Cost
₹3800 Cr
Latest approved cost
Expenditure
₹979 Cr
Spent to date
Utilization
25.8%
Of revised budget
Cost Status
+104.7%
+₹1944 Cr increase
Remaining
₹2821 Cr
Budget left
Spent
₹979 Cr
Remaining
₹2821 Cr
Total
₹3800 Cr
Original Cost
₹1856 Cr
Revised Cost
₹3800 Cr
Increase
+₹1944 Cr
Escalation
+104.7%
Project Approved
Construction / Implementation
Original End Date
30/04/2020
Revised Completion
31/03/2029
Completed
Cost has increased by ₹1944 Cr (104.7%) from the original estimate of ₹1856 Cr.
Expenditure stands at ₹979 Cr, which is 25.8% of the revised project cost.
Remaining budget: ₹2821 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Mines.