Original Cost
₹355 Cr
Baseline estimate
Revised Cost
₹581 Cr
Latest approved cost
Expenditure
₹164 Cr
Spent to date
Utilization
28.1%
Of revised budget
Cost Status
+63.7%
+₹226 Cr increase
Remaining
₹417 Cr
Budget left
Spent
₹164 Cr
Remaining
₹417 Cr
Total
₹581 Cr
Original Cost
₹355 Cr
Revised Cost
₹581 Cr
Increase
+₹226 Cr
Escalation
+63.7%
Project Approved
Construction / Implementation
Original End Date
30/11/2026
Revised Completion
Completed
Cost has increased by ₹226 Cr (63.7%) from the original estimate of ₹355 Cr.
Expenditure stands at ₹164 Cr, which is 28.1% of the revised project cost.
Remaining budget: ₹417 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Mines.