Original Cost
₹4103 Cr
Baseline estimate
Revised Cost
₹5677 Cr
Latest approved cost
Expenditure
₹4920 Cr
Spent to date
Utilization
86.7%
Of revised budget
Cost Status
+38.4%
+₹1574 Cr increase
Remaining
₹757 Cr
Budget left
Spent
₹4920 Cr
Remaining
₹757 Cr
Total
₹5677 Cr
Original Cost
₹4103 Cr
Revised Cost
₹5677 Cr
Increase
+₹1574 Cr
Escalation
+38.4%
Project Approved
Construction / Implementation
Original End Date
31/12/2022
Revised Completion
30/06/2026
Completed
Cost has increased by ₹1574 Cr (38.4%) from the original estimate of ₹4103 Cr.
Expenditure stands at ₹4920 Cr, which is 86.7% of the revised project cost.
Remaining budget: ₹757 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Metals & Mining. Ministry: Ministry of Mines.