Original Cost
₹1800 Cr
Baseline estimate
Revised Cost
₹2564 Cr
Latest approved cost
Expenditure
₹1713 Cr
Spent to date
Utilization
66.8%
Of revised budget
Cost Status
+42.5%
+₹764 Cr increase
Remaining
₹851 Cr
Budget left
Spent
₹1713 Cr
Remaining
₹851 Cr
Total
₹2564 Cr
Original Cost
₹1800 Cr
Revised Cost
₹2564 Cr
Increase
+₹764 Cr
Escalation
+42.5%
Project Approved
Construction / Implementation
Original End Date
30/06/2025
Revised Completion
30/06/2027
Completed
Cost has increased by ₹764 Cr (42.5%) from the original estimate of ₹1800 Cr.
Expenditure stands at ₹1713 Cr, which is 66.8% of the revised project cost.
Remaining budget: ₹851 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Coal.