RailwaysIPM · Central Project#616697

3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Gangavaram Port-Visakhapatnam Steel Plant12.04 km PB73/2023-24/NR

Ministry of RailwaysAndhra Pradesh
Revised Cost: ₹154 CrUtilization: 58.2%

Original Cost

₹154 Cr

Baseline estimate

On budget

Revised Cost

₹154 Cr

Latest approved cost

Expenditure

₹90 Cr

Spent to date

Utilization

58.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹64 Cr

Budget left

Budget Utilization

58.2%
0%25%50%75%100%

Spent

₹90 Cr

Remaining

₹64 Cr

Total

₹154 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

30/06/2026

Revised Completion

Completed

Project Details

Project Code616697
SectorRailways
MinistryMinistry of Railways
StateAndhra Pradesh
Data Month2026-08

Financial Summary

Original Cost₹154 Cr
Revised Cost₹154 Cr
Expenditure₹90 Cr
Original End Date30/06/2026
Revised DateN/A

Project Intelligence

Project is within original budget of ₹154 Cr — no cost escalation recorded.

Expenditure stands at ₹90 Cr, which is 58.2% of the revised project cost.

Remaining budget: ₹64 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Gangavaram Port-Visakhapatnam Steel Plant12.04 km PB73/2023-24/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹154.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Gangavaram Port-Visakh"?
3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Gangavaram Port-Visakhapatnam Steel Plant12.04 km PB73/2023-24/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Andhra Pradesh. Original cost: ₹154 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹154 Cr has not been significantly revised. Expenditure: ₹90 Cr (58.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Ga is under the Ministry of Railways in the Railways sector. Project code: 616697. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 3rd & 4 th line Vadlapudi-Gate Jn. incl. tie line between Ga is one of several Bihar projects tracked under the Railways sector on the IPM system.