3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23
Original Cost
₹168 Cr
Baseline estimate
Revised Cost
₹168 Cr
Latest approved cost
Expenditure
₹28 Cr
Spent to date
Utilization
17.0%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹140 Cr
Budget left
Budget Utilization
17.0%Spent
₹28 Cr
Remaining
₹140 Cr
Total
₹168 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹168 Cr — no cost escalation recorded.
Expenditure stands at ₹28 Cr, which is 17.0% of the revised project cost.
Remaining budget: ₹140 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹168.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23"?
- 3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹168 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹168 Cr has not been significantly revised. Expenditure: ₹28 Cr (17.0% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/202 is under the Ministry of Railways in the Railways sector. Project code: 709819. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/202 is one of several Bihar projects tracked under the Railways sector on the IPM system.