3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23

Ministry of RailwaysChhattisgarh
Revised Cost: ₹168 CrUtilization: 17.0%

Original Cost

₹168 Cr

Baseline estimate

On budget

Revised Cost

₹168 Cr

Latest approved cost

Expenditure

₹28 Cr

Spent to date

Utilization

17.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹140 Cr

Budget left

Budget Utilization

17.0%
0%25%50%75%100%

Spent

₹28 Cr

Remaining

₹140 Cr

Total

₹168 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code709819
SectorRailways
MinistryMinistry of Railways
StateChhattisgarh
Data Month2026-08

Financial Summary

Original Cost₹168 Cr
Revised Cost₹168 Cr
Expenditure₹28 Cr
Original End Date31/12/2026
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹168 Cr — no cost escalation recorded.

Expenditure stands at ₹28 Cr, which is 17.0% of the revised project cost.

Remaining budget: ₹140 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹168.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23"?
3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/2022-23 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹168 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹168 Cr has not been significantly revised. Expenditure: ₹28 Cr (17.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/202 is under the Ministry of Railways in the Railways sector. Project code: 709819. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 3rd & 4th line - Saragbundia & Madwarani 12.2 km PB72/NR/202 is one of several Bihar projects tracked under the Railways sector on the IPM system.