RailwaysIPM · Central Project +80.7% overrun#705506

3rd Line Manmad - Jalgaon [160 Kilometres]

Ministry of RailwaysMaharashtra
Revised Cost: ₹1870 CrUtilization: 98.6%Overrun: +₹835 Cr

Original Cost

₹1035 Cr

Baseline estimate

+81% overrun

Revised Cost

₹1870 Cr

Latest approved cost

Expenditure

₹1844 Cr

Spent to date

Utilization

98.6%

Of revised budget

Escalated

Cost Status

+80.7%

+₹835 Cr increase

Remaining

₹26 Cr

Budget left

Budget Utilization

98.6%
0%25%50%75%100%

Spent

₹1844 Cr

Remaining

₹26 Cr

Total

₹1870 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1035 Cr

Revised Cost

₹1870 Cr

Increase

+₹835 Cr

Escalation

+80.7%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2024

Revised Completion

24/11/2025

Completed

Project Details

Project Code705506
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-07

Financial Summary

Original Cost₹1035 Cr
Revised Cost₹1870 Cr
Expenditure₹1844 Cr
Original End Date31/12/2024
Revised Date24/11/2025

Project Intelligence

Cost has increased by ₹835 Cr (80.7%) from the original estimate of ₹1035 Cr.

Expenditure stands at ₹1844 Cr, which is 98.6% of the revised project cost.

Remaining budget: ₹26 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

3rd Line Manmad - Jalgaon [160 Kilometres] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1035.00 Cr, later revised to ₹1870.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "3rd Line Manmad - Jalgaon [160 Kilometres]"?
3rd Line Manmad - Jalgaon [160 Kilometres] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹1035 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1035 Cr and has been revised to ₹1870 Cr — a cost overrun of +80.7%. Expenditure to date: ₹1844 Cr (98.6% of revised cost). Data as of 2026-07.
QWhich ministry is responsible for this project?
3rd Line Manmad - Jalgaon [160 Kilometres] is under the Ministry of Railways in the Railways sector. Project code: 705506. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 3rd Line Manmad - Jalgaon [160 Kilometres] is one of several Bihar projects tracked under the Railways sector on the IPM system.