3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR
Original Cost
₹252 Cr
Baseline estimate
Revised Cost
₹252 Cr
Latest approved cost
Expenditure
₹188 Cr
Spent to date
Utilization
74.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹64 Cr
Budget left
Budget Utilization
74.7%Spent
₹188 Cr
Remaining
₹64 Cr
Total
₹252 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
28/12/2025
Revised Completion
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹252 Cr — no cost escalation recorded.
Expenditure stands at ₹188 Cr, which is 74.7% of the revised project cost.
Remaining budget: ₹64 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹252.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR"?
- 3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹252 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost of ₹252 Cr has not been significantly revised. Expenditure: ₹188 Cr (74.7% of cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- 3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR is under the Ministry of Railways in the Railways sector. Project code: 612834. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. 3rd & 4th line between Sarla - Sason 8 km PB73/2023-24/NR is one of several Bihar projects tracked under the Railways sector on the IPM system.