Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/2018-19/NR
Original Cost
₹1454 Cr
Baseline estimate
Revised Cost
₹456 Cr
Latest approved cost
Expenditure
₹108 Cr
Spent to date
Utilization
23.6%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹348 Cr
Budget left
Budget Utilization
23.6%Spent
₹108 Cr
Remaining
₹348 Cr
Total
₹456 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
01/12/2027
Revised Completion
30/06/2028
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹1454 Cr — no cost escalation recorded.
Expenditure stands at ₹108 Cr, which is 23.6% of the revised project cost.
Remaining budget: ₹348 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/2018-19/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1454.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/2018-19/NR"?
- Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/2018-19/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Karnataka. Original cost: ₹1454 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1454 Cr and has been revised to ₹456 Cr — a cost overrun of -68.6%. Expenditure to date: ₹108 Cr (23.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/201 is under the Ministry of Railways in the Railways sector. Project code: 705761. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Shimoga-Shikaripura-Ranebennur 103 km umbrella work PB23/201 is one of several Bihar projects tracked under the Railways sector on the IPM system.