Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR
Original Cost
₹304 Cr
Baseline estimate
Revised Cost
₹239 Cr
Latest approved cost
Expenditure
₹188 Cr
Spent to date
Utilization
78.7%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹51 Cr
Budget left
Budget Utilization
78.7%Spent
₹188 Cr
Remaining
₹51 Cr
Total
₹239 Cr
Budget Split
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
27/05/2027
Completed
Project Details
Financial Summary
Project Intelligence
Project is within original budget of ₹304 Cr — no cost escalation recorded.
Expenditure stands at ₹188 Cr, which is 78.7% of the revised project cost.
Remaining budget: ₹51 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹304.00 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR"?
- Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Rajasthan. Original cost: ₹304 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹304 Cr and has been revised to ₹239 Cr — a cost overrun of -21.4%. Expenditure to date: ₹188 Cr (78.7% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019- is under the Ministry of Railways in the Railways sector. Project code: 706866. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019- is one of several Bihar projects tracked under the Railways sector on the IPM system.