RailwaysIPM · Central Project#706866

Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR

Ministry of RailwaysRajasthan
Revised Cost: ₹239 CrUtilization: 78.7%

Original Cost

₹304 Cr

Baseline estimate

On budget

Revised Cost

₹239 Cr

Latest approved cost

Expenditure

₹188 Cr

Spent to date

Utilization

78.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹51 Cr

Budget left

Budget Utilization

78.7%
0%25%50%75%100%

Spent

₹188 Cr

Remaining

₹51 Cr

Total

₹239 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2026

Revised Completion

27/05/2027

Completed

Project Details

Project Code706866
SectorRailways
MinistryMinistry of Railways
StateRajasthan
Data Month2026-08

Financial Summary

Original Cost₹304 Cr
Revised Cost₹239 Cr
Expenditure₹188 Cr
Original End Date31/03/2026
Revised Date27/05/2027

Project Intelligence

Project is within original budget of ₹304 Cr — no cost escalation recorded.

Expenditure stands at ₹188 Cr, which is 78.7% of the revised project cost.

Remaining budget: ₹51 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹304.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR"?
Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019-20/NR is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Rajasthan. Original cost: ₹304 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹304 Cr and has been revised to ₹239 Cr — a cost overrun of -21.4%. Expenditure to date: ₹188 Cr (78.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019- is under the Ministry of Railways in the Railways sector. Project code: 706866. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Sawaimadhopur - Bypass line 6.98 km Umbrella work PB57/2019- is one of several Bihar projects tracked under the Railways sector on the IPM system.