RailwaysIPM · Central Project#611970

Samlaya-Timba Road 53.53 km

Ministry of RailwaysGujarat
Revised Cost: ₹670 CrUtilization: 30.2%

Original Cost

₹670 Cr

Baseline estimate

On budget

Revised Cost

₹670 Cr

Latest approved cost

Expenditure

₹203 Cr

Spent to date

Utilization

30.2%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹468 Cr

Budget left

Budget Utilization

30.2%
0%25%50%75%100%

Spent

₹203 Cr

Remaining

₹468 Cr

Total

₹670 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2030

Revised Completion

30/03/2030

Completed

Project Details

Project Code611970
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹670 Cr
Revised Cost₹670 Cr
Expenditure₹203 Cr
Original End Date31/03/2030
Revised Date30/03/2030

Project Intelligence

Project is within original budget of ₹670 Cr — no cost escalation recorded.

Expenditure stands at ₹203 Cr, which is 30.2% of the revised project cost.

Remaining budget: ₹468 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Samlaya-Timba Road 53.53 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹670.00 Cr, later revised to ₹670.17 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Samlaya-Timba Road 53.53 km"?
Samlaya-Timba Road 53.53 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹670 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹670 Cr has not been significantly revised. Expenditure: ₹203 Cr (30.2% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Samlaya-Timba Road 53.53 km is under the Ministry of Railways in the Railways sector. Project code: 611970. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Samlaya-Timba Road 53.53 km is one of several Bihar projects tracked under the Railways sector on the IPM system.