Original Cost
₹1441 Cr
Baseline estimate
Revised Cost
₹2462 Cr
Latest approved cost
Expenditure
₹2337 Cr
Spent to date
Utilization
94.9%
Of revised budget
Cost Status
+70.9%
+₹1021 Cr increase
Remaining
₹125 Cr
Budget left
Spent
₹2337 Cr
Remaining
₹125 Cr
Total
₹2462 Cr
Original Cost
₹1441 Cr
Revised Cost
₹2462 Cr
Increase
+₹1021 Cr
Escalation
+70.9%
Project Approved
Construction / Implementation
Original End Date
30/06/2021
Revised Completion
30/06/2026
Completed
Cost has increased by ₹1021 Cr (70.9%) from the original estimate of ₹1441 Cr.
Expenditure stands at ₹2337 Cr, which is 94.9% of the revised project cost.
Remaining budget: ₹125 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.