Arjun Sahayak Project
Original Cost
₹741 Cr
Baseline estimate
Revised Cost
₹2466 Cr
Latest approved cost
Expenditure
₹3218 Cr
Spent to date
Utilization
130.5%
Of revised budget
Cost Status
+232.8%
+₹1725 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
130.5%Spent
₹3218 Cr
Remaining
₹0 Cr
Total
₹2466 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹741 Cr
Revised Cost
₹2466 Cr
Increase
+₹1725 Cr
Escalation
+232.8%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2019
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹1725 Cr (232.8%) from the original estimate of ₹741 Cr.
Expenditure stands at ₹3218 Cr, which is 130.5% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.
Arjun Sahayak Project is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹741.00 Cr, later revised to ₹2465.68 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Arjun Sahayak Project"?
- Arjun Sahayak Project is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Uttar Pradesh. Original cost: ₹741 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹741 Cr and has been revised to ₹2466 Cr — a cost overrun of +232.8%. Expenditure to date: ₹3218 Cr (130.5% of revised cost). Data as of 2025-08.
- QWhich ministry is responsible for this project?
- Arjun Sahayak Project is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 400117. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Arjun Sahayak Project is one of several Bihar projects tracked under the Water Resources sector on the IPM system.