Original Cost
₹751 Cr
Baseline estimate
Revised Cost
₹893 Cr
Latest approved cost
Expenditure
₹814 Cr
Spent to date
Utilization
91.1%
Of revised budget
Cost Status
+19.0%
+₹142 Cr increase
Remaining
₹79 Cr
Budget left
Spent
₹814 Cr
Remaining
₹79 Cr
Total
₹893 Cr
Original Cost
₹751 Cr
Revised Cost
₹893 Cr
Increase
+₹142 Cr
Escalation
+19.0%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/03/2026
Completed
Cost has increased by ₹142 Cr (19.0%) from the original estimate of ₹751 Cr.
Expenditure stands at ₹814 Cr, which is 91.1% of the revised project cost.
Remaining budget: ₹79 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.