Water ResourcesIPM · Central Project +19.0% overrun#400115

Bargi Diversion Project Phase - IV [km. 154 to km 197]

Department of Water Resources, River Development & GRMadhya Pradesh
Revised Cost: ₹893 CrUtilization: 91.1%Overrun: +₹142 Cr

Original Cost

₹751 Cr

Baseline estimate

+19% overrun

Revised Cost

₹893 Cr

Latest approved cost

Expenditure

₹814 Cr

Spent to date

Utilization

91.1%

Of revised budget

Escalated

Cost Status

+19.0%

+₹142 Cr increase

Remaining

₹79 Cr

Budget left

Budget Utilization

91.1%
0%25%50%75%100%

Spent

₹814 Cr

Remaining

₹79 Cr

Total

₹893 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹751 Cr

Revised Cost

₹893 Cr

Increase

+₹142 Cr

Escalation

+19.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2019

Revised Completion

31/03/2026

Completed

Project Details

Project Code400115
SectorWater Resources
MinistryDepartment of Water Resources, River Development & GR
StateMadhya Pradesh
Data Month2026-08

Financial Summary

Original Cost₹751 Cr
Revised Cost₹893 Cr
Expenditure₹814 Cr
Original End Date31/12/2019
Revised Date31/03/2026

Project Intelligence

Cost has increased by ₹142 Cr (19.0%) from the original estimate of ₹751 Cr.

Expenditure stands at ₹814 Cr, which is 91.1% of the revised project cost.

Remaining budget: ₹79 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.

Bargi Diversion Project Phase - IV [km. 154 to km 197] is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹751.00 Cr, later revised to ₹893.35 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Bargi Diversion Project Phase - IV [km. 154 to km 197]"?
Bargi Diversion Project Phase - IV [km. 154 to km 197] is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Madhya Pradesh. Original cost: ₹751 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹751 Cr and has been revised to ₹893 Cr — a cost overrun of +19%. Expenditure to date: ₹814 Cr (91.1% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Bargi Diversion Project Phase - IV [km. 154 to km 197] is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 400115. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bargi Diversion Project Phase - IV [km. 154 to km 197] is one of several Bihar projects tracked under the Water Resources sector on the IPM system.