Bargi Diversion Project Phase - III [km. 104 to km 154]
Original Cost
₹1229 Cr
Baseline estimate
Revised Cost
₹1400 Cr
Latest approved cost
Expenditure
₹2272 Cr
Spent to date
Utilization
162.3%
Of revised budget
Cost Status
+13.9%
+₹171 Cr increase
Remaining
₹0 Cr
Budget left
Budget Utilization
162.3%Spent
₹2272 Cr
Remaining
₹0 Cr
Total
₹1400 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹1229 Cr
Revised Cost
₹1400 Cr
Increase
+₹171 Cr
Escalation
+13.9%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹171 Cr (13.9%) from the original estimate of ₹1229 Cr.
Expenditure stands at ₹2272 Cr, which is 162.3% of the revised project cost.
Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.
Bargi Diversion Project Phase - III [km. 104 to km 154] is a centrally-funded infrastructure project under Department of Water Resources, River Development & GR, in the Water Resources sector. The original approved cost is ₹1229.00 Cr, later revised to ₹1399.70 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Bargi Diversion Project Phase - III [km. 104 to km 154]"?
- Bargi Diversion Project Phase - III [km. 104 to km 154] is a centrally-funded infrastructure project under the Department of Water Resources, River Development & GR, tracked through the Investment Project Monitoring (IPM) system. Sector: Water Resources. State: Madhya Pradesh. Original cost: ₹1229 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹1229 Cr and has been revised to ₹1400 Cr — a cost overrun of +13.9%. Expenditure to date: ₹2272 Cr (162.3% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Bargi Diversion Project Phase - III [km. 104 to km 154] is under the Department of Water Resources, River Development & GR in the Water Resources sector. Project code: 400116. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Bargi Diversion Project Phase - III [km. 104 to km 154] is one of several Bihar projects tracked under the Water Resources sector on the IPM system.