Original Cost
₹334 Cr
Baseline estimate
Revised Cost
₹611 Cr
Latest approved cost
Expenditure
₹804 Cr
Spent to date
Utilization
131.6%
Of revised budget
Cost Status
+82.9%
+₹277 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹804 Cr
Remaining
₹0 Cr
Total
₹611 Cr
Original Cost
₹334 Cr
Revised Cost
₹611 Cr
Increase
+₹277 Cr
Escalation
+82.9%
Project Approved
Construction / Implementation
Original End Date
31/12/2019
Revised Completion
31/12/2024
Completed
Cost has increased by ₹277 Cr (82.9%) from the original estimate of ₹334 Cr.
Expenditure stands at ₹804 Cr, which is 131.6% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Water Resources. Ministry: Department of Water Resources, River Development & GR.