Original Cost
₹842 Cr
Baseline estimate
Revised Cost
₹842 Cr
Latest approved cost
Expenditure
₹340 Cr
Spent to date
Utilization
40.4%
Of revised budget
Cost Status
On Budget
No escalation
Remaining
₹502 Cr
Budget left
Spent
₹340 Cr
Remaining
₹502 Cr
Total
₹842 Cr
Project Approved
Construction / Implementation
Original End Date
31/03/2026
Revised Completion
Completed
Project is within original budget of ₹842 Cr — no cost escalation recorded.
Expenditure stands at ₹340 Cr, which is 40.4% of the revised project cost.
Remaining budget: ₹502 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.