Original Cost
₹4028 Cr
Baseline estimate
Revised Cost
₹4873 Cr
Latest approved cost
Expenditure
₹5249 Cr
Spent to date
Utilization
107.7%
Of revised budget
Cost Status
+21.0%
+₹845 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹5249 Cr
Remaining
₹0 Cr
Total
₹4873 Cr
Original Cost
₹4028 Cr
Revised Cost
₹4873 Cr
Increase
+₹845 Cr
Escalation
+21.0%
Project Approved
Construction / Implementation
Original End Date
28/02/2025
Revised Completion
31/08/2025
Completed
Cost has increased by ₹845 Cr (21.0%) from the original estimate of ₹4028 Cr.
Expenditure stands at ₹5249 Cr, which is 107.7% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.