RailwaysIPM · Central Project +21.0% overrun#705503

Pune - Miraj-Londa [467 Kilometres]

Ministry of RailwaysMaharashtra
Revised Cost: ₹4873 CrUtilization: 107.7%Overrun: +₹845 Cr

Original Cost

₹4028 Cr

Baseline estimate

+21% overrun

Revised Cost

₹4873 Cr

Latest approved cost

Expenditure

₹5249 Cr

Spent to date

Utilization

107.7%

Of revised budget

Escalated

Cost Status

+21.0%

+₹845 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

107.7%
0%25%50%75%100%

Spent

₹5249 Cr

Remaining

₹0 Cr

Total

₹4873 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹4028 Cr

Revised Cost

₹4873 Cr

Increase

+₹845 Cr

Escalation

+21.0%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

28/02/2025

Revised Completion

31/08/2025

Completed

Project Details

Project Code705503
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-03

Financial Summary

Original Cost₹4028 Cr
Revised Cost₹4873 Cr
Expenditure₹5249 Cr
Original End Date28/02/2025
Revised Date31/08/2025

Project Intelligence

Cost has increased by ₹845 Cr (21.0%) from the original estimate of ₹4028 Cr.

Expenditure stands at ₹5249 Cr, which is 107.7% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Pune - Miraj-Londa [467 Kilometres] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹4028.00 Cr, later revised to ₹4872.52 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pune - Miraj-Londa [467 Kilometres]"?
Pune - Miraj-Londa [467 Kilometres] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹4028 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹4028 Cr and has been revised to ₹4873 Cr — a cost overrun of +21%. Expenditure to date: ₹5249 Cr (107.7% of revised cost). Data as of 2026-03.
QWhich ministry is responsible for this project?
Pune - Miraj-Londa [467 Kilometres] is under the Ministry of Railways in the Railways sector. Project code: 705503. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pune - Miraj-Londa [467 Kilometres] is one of several Bihar projects tracked under the Railways sector on the IPM system.