Original Cost
₹349 Cr
Baseline estimate
Revised Cost
₹349 Cr
Latest approved cost
Expenditure
₹146 Cr
Spent to date
Utilization
41.7%
Of revised budget
Cost Status
+0.1%
+₹0 Cr increase
Remaining
₹204 Cr
Budget left
Spent
₹146 Cr
Remaining
₹204 Cr
Total
₹349 Cr
Original Cost
₹349 Cr
Revised Cost
₹349 Cr
Increase
+₹0 Cr
Escalation
+0.1%
Project Approved
Construction / Implementation
Original End Date
30/11/2027
Revised Completion
27/11/2027
Completed
Cost has increased by ₹0 Cr (0.1%) from the original estimate of ₹349 Cr.
Expenditure stands at ₹146 Cr, which is 41.7% of the revised project cost.
Remaining budget: ₹204 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.