RailwaysIPM · Central Project +119.2% overrun#612845

Pachora-Jamner with extension upto Malkapur-Narrow gauge to broad gauge 84 km

Ministry of RailwaysMaharashtra
Revised Cost: ₹2094 CrUtilization: 14.7%Overrun: +₹1139 Cr

Original Cost

₹955 Cr

Baseline estimate

+119% overrun

Revised Cost

₹2094 Cr

Latest approved cost

Expenditure

₹308 Cr

Spent to date

Utilization

14.7%

Of revised budget

Escalated

Cost Status

+119.2%

+₹1139 Cr increase

Remaining

₹1786 Cr

Budget left

Budget Utilization

14.7%
0%25%50%75%100%

Spent

₹308 Cr

Remaining

₹1786 Cr

Total

₹2094 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹955 Cr

Revised Cost

₹2094 Cr

Increase

+₹1139 Cr

Escalation

+119.2%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/08/2027

Revised Completion

Completed

Project Details

Project Code612845
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-08

Financial Summary

Original Cost₹955 Cr
Revised Cost₹2094 Cr
Expenditure₹308 Cr
Original End Date31/08/2027
Revised DateN/A

Project Intelligence

Cost has increased by ₹1139 Cr (119.2%) from the original estimate of ₹955 Cr.

Expenditure stands at ₹308 Cr, which is 14.7% of the revised project cost.

Remaining budget: ₹1786 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Pachora-Jamner with extension upto Malkapur-Narrow gauge to broad gauge 84 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹955.00 Cr, later revised to ₹2093.82 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Pachora-Jamner with extension upto Malkapur-Narrow gauge to broad gauge 84 km"?
Pachora-Jamner with extension upto Malkapur-Narrow gauge to broad gauge 84 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹955 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹955 Cr and has been revised to ₹2094 Cr — a cost overrun of +119.2%. Expenditure to date: ₹308 Cr (14.7% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Pachora-Jamner with extension upto Malkapur-Narrow gauge to is under the Ministry of Railways in the Railways sector. Project code: 612845. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Pachora-Jamner with extension upto Malkapur-Narrow gauge to is one of several Bihar projects tracked under the Railways sector on the IPM system.