RailwaysIPM · Central Project +144.3% overrun#709813

New BG line intersection 5 nos between Geratpur-Sanand & Botad-Ahmedabad 16.51 km PB29/NR/2022-23

Ministry of RailwaysGujarat
Revised Cost: ₹1067 CrUtilization: 56.5%Overrun: +₹630 Cr

Original Cost

₹437 Cr

Baseline estimate

+144% overrun

Revised Cost

₹1067 Cr

Latest approved cost

Expenditure

₹603 Cr

Spent to date

Utilization

56.5%

Of revised budget

Escalated

Cost Status

+144.3%

+₹630 Cr increase

Remaining

₹465 Cr

Budget left

Budget Utilization

56.5%
0%25%50%75%100%

Spent

₹603 Cr

Remaining

₹465 Cr

Total

₹1067 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹437 Cr

Revised Cost

₹1067 Cr

Increase

+₹630 Cr

Escalation

+144.3%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/10/2027

Revised Completion

27/10/2027

Completed

Project Details

Project Code709813
SectorRailways
MinistryMinistry of Railways
StateGujarat
Data Month2026-08

Financial Summary

Original Cost₹437 Cr
Revised Cost₹1067 Cr
Expenditure₹603 Cr
Original End Date31/10/2027
Revised Date27/10/2027

Project Intelligence

Cost has increased by ₹630 Cr (144.3%) from the original estimate of ₹437 Cr.

Expenditure stands at ₹603 Cr, which is 56.5% of the revised project cost.

Remaining budget: ₹465 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

New BG line intersection 5 nos between Geratpur-Sanand & Botad-Ahmedabad 16.51 km PB29/NR/2022-23 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹437.00 Cr, later revised to ₹1067.45 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "New BG line intersection 5 nos between Geratpur-Sanand & Botad-Ahmedabad 16.51 k"?
New BG line intersection 5 nos between Geratpur-Sanand & Botad-Ahmedabad 16.51 km PB29/NR/2022-23 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Gujarat. Original cost: ₹437 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹437 Cr and has been revised to ₹1067 Cr — a cost overrun of +144.3%. Expenditure to date: ₹603 Cr (56.5% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
New BG line intersection 5 nos between Geratpur-Sanand & Bot is under the Ministry of Railways in the Railways sector. Project code: 709813. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. New BG line intersection 5 nos between Geratpur-Sanand & Bot is one of several Bihar projects tracked under the Railways sector on the IPM system.