RailwaysIPM · Central Project#611452

MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKM

Ministry of RailwaysMaharashtra
Revised Cost: ₹311 CrUtilization: 84.7%

Original Cost

₹311 Cr

Baseline estimate

On budget

Revised Cost

₹311 Cr

Latest approved cost

Expenditure

₹263 Cr

Spent to date

Utilization

84.7%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹48 Cr

Budget left

Budget Utilization

84.7%
0%25%50%75%100%

Spent

₹263 Cr

Remaining

₹48 Cr

Total

₹311 Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2025

Revised Completion

31/12/2026

Completed

Project Details

Project Code611452
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-06

Financial Summary

Original Cost₹311 Cr
Revised Cost₹311 Cr
Expenditure₹263 Cr
Original End Date31/12/2025
Revised Date31/12/2026

Project Intelligence

Project is within original budget of ₹311 Cr — no cost escalation recorded.

Expenditure stands at ₹263 Cr, which is 84.7% of the revised project cost.

Remaining budget: ₹48 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKM is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹311.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKM"?
MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SYSTEM 500 RKM is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹311 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹311 Cr has not been significantly revised. Expenditure: ₹263 Cr (84.7% of cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SY is under the Ministry of Railways in the Railways sector. Project code: 611452. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. MUMBAI CENTRAL VIRAR VADODARA AHMEDABAAD TRAIN PROTECTION SY is one of several Bihar projects tracked under the Railways sector on the IPM system.