RailwaysIPM · Central Project#616699

Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB34/ECOR/2023-24

Ministry of RailwaysWest Bengal
Revised Cost: ₹12.3K CrUtilization: 11.0%

Original Cost

₹12.3K Cr

Baseline estimate

On budget

Revised Cost

₹12.3K Cr

Latest approved cost

Expenditure

₹1351 Cr

Spent to date

Utilization

11.0%

Of revised budget

Stable

Cost Status

On Budget

No escalation

Remaining

₹11.0K Cr

Budget left

Budget Utilization

11.0%
0%25%50%75%100%

Spent

₹1351 Cr

Remaining

₹11.0K Cr

Total

₹12.3K Cr

Budget Split

SpentRemaining

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2028

Revised Completion

Completed

Project Details

Project Code616699
SectorRailways
MinistryMinistry of Railways
StateWest Bengal
Data Month2026-08

Financial Summary

Original Cost₹12.3K Cr
Revised Cost₹12.3K Cr
Expenditure₹1351 Cr
Original End Date31/03/2028
Revised DateN/A

Project Intelligence

Mega infrastructure project worth ₹12.3K Cr — among the largest central projects in West Bengal.

Project is within original budget of ₹12.3K Cr — no cost escalation recorded.

Expenditure stands at ₹1351 Cr, which is 11.0% of the revised project cost.

Remaining budget: ₹11.0K Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB34/ECOR/2023-24 is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹12334.00 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB34/ECOR/2023-24"?
Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB34/ECOR/2023-24 is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: West Bengal. Original cost: ₹12334 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost of ₹12334 Cr has not been significantly revised. Expenditure: ₹1351 Cr (11.0% of cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB is under the Ministry of Railways in the Railways sector. Project code: 616699. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Multi tracking of Son Nagar-Andal 374.53 rkm & 814.38 tkm PB is one of several Bihar projects tracked under the Railways sector on the IPM system.