RailwaysIPM · Central Project +64.1% overrun#705358

Khurda Road-Bolangir 301 km

Ministry of RailwaysOdisha
Revised Cost: ₹6222 CrUtilization: 78.2%Overrun: +₹2430 Cr

Original Cost

₹3792 Cr

Baseline estimate

+64% overrun

Revised Cost

₹6222 Cr

Latest approved cost

Expenditure

₹4865 Cr

Spent to date

Utilization

78.2%

Of revised budget

Escalated

Cost Status

+64.1%

+₹2430 Cr increase

Remaining

₹1357 Cr

Budget left

Budget Utilization

78.2%
0%25%50%75%100%

Spent

₹4865 Cr

Remaining

₹1357 Cr

Total

₹6222 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹3792 Cr

Revised Cost

₹6222 Cr

Increase

+₹2430 Cr

Escalation

+64.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

31/12/2026

Completed

Project Details

Project Code705358
SectorRailways
MinistryMinistry of Railways
StateOdisha
Data Month2026-08

Financial Summary

Original Cost₹3792 Cr
Revised Cost₹6222 Cr
Expenditure₹4865 Cr
Original End Date31/12/2026
Revised Date31/12/2026

Project Intelligence

Cost has increased by ₹2430 Cr (64.1%) from the original estimate of ₹3792 Cr.

Expenditure stands at ₹4865 Cr, which is 78.2% of the revised project cost.

Remaining budget: ₹1357 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Khurda Road-Bolangir 301 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹3792.00 Cr, later revised to ₹6221.98 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Khurda Road-Bolangir 301 km"?
Khurda Road-Bolangir 301 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Odisha. Original cost: ₹3792 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹3792 Cr and has been revised to ₹6222 Cr — a cost overrun of +64.1%. Expenditure to date: ₹4865 Cr (78.2% of revised cost). Data as of 2026-08.
QWhich ministry is responsible for this project?
Khurda Road-Bolangir 301 km is under the Ministry of Railways in the Railways sector. Project code: 705358. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Khurda Road-Bolangir 301 km is one of several Bihar projects tracked under the Railways sector on the IPM system.