Original Cost
₹726 Cr
Baseline estimate
Revised Cost
₹836 Cr
Latest approved cost
Expenditure
₹9 Cr
Spent to date
Utilization
1.1%
Of revised budget
Cost Status
+15.2%
+₹110 Cr increase
Remaining
₹827 Cr
Budget left
Spent
₹9 Cr
Remaining
₹827 Cr
Total
₹836 Cr
Original Cost
₹726 Cr
Revised Cost
₹836 Cr
Increase
+₹110 Cr
Escalation
+15.2%
Project Approved
Construction / Implementation
Original End Date
31/03/2027
Revised Completion
27/03/2027
Completed
Cost has increased by ₹110 Cr (15.2%) from the original estimate of ₹726 Cr.
Expenditure stands at ₹9 Cr, which is 1.1% of the revised project cost.
Remaining budget: ₹827 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.