Kalyan-Kasara - 3rd line 67.62 km
Original Cost
₹793 Cr
Baseline estimate
Revised Cost
₹1396 Cr
Latest approved cost
Expenditure
₹1166 Cr
Spent to date
Utilization
83.6%
Of revised budget
Cost Status
+76.0%
+₹603 Cr increase
Remaining
₹230 Cr
Budget left
Budget Utilization
83.6%Spent
₹1166 Cr
Remaining
₹230 Cr
Total
₹1396 Cr
Budget Split
Cost Escalation Analysis
Original Cost
₹793 Cr
Revised Cost
₹1396 Cr
Increase
+₹603 Cr
Escalation
+76.0%
Project Timeline
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
31/12/2026
Completed
Project Details
Financial Summary
Project Intelligence
Cost has increased by ₹603 Cr (76.0%) from the original estimate of ₹793 Cr.
Expenditure stands at ₹1166 Cr, which is 83.6% of the revised project cost.
Remaining budget: ₹230 Cr. Tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.
Kalyan-Kasara - 3rd line 67.62 km is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹793.00 Cr, later revised to ₹1395.50 Cr.
This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.
Frequently Asked Questions
- QWhat is IPM project "Kalyan-Kasara - 3rd line 67.62 km"?
- Kalyan-Kasara - 3rd line 67.62 km is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹793 Cr.
- QWhat is the cost overrun for this Bihar IPM project?
- The original cost was ₹793 Cr and has been revised to ₹1396 Cr — a cost overrun of +76%. Expenditure to date: ₹1166 Cr (83.6% of revised cost). Data as of 2026-08.
- QWhich ministry is responsible for this project?
- Kalyan-Kasara - 3rd line 67.62 km is under the Ministry of Railways in the Railways sector. Project code: 705498. Bihar is one of the states tracked under the central IPM dashboard for this project.
- QWhat is the IPM dashboard and what does it track?
- The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Kalyan-Kasara - 3rd line 67.62 km is one of several Bihar projects tracked under the Railways sector on the IPM system.