Original Cost
₹493 Cr
Baseline estimate
Revised Cost
₹1171 Cr
Latest approved cost
Expenditure
₹542 Cr
Spent to date
Utilization
46.3%
Of revised budget
Cost Status
+137.5%
+₹678 Cr increase
Remaining
₹629 Cr
Budget left
Spent
₹542 Cr
Remaining
₹629 Cr
Total
₹1171 Cr
Original Cost
₹493 Cr
Revised Cost
₹1171 Cr
Increase
+₹678 Cr
Escalation
+137.5%
Project Approved
Construction / Implementation
Original End Date
31/12/2026
Revised Completion
30/09/2027
Completed
Cost has increased by ₹678 Cr (137.5%) from the original estimate of ₹493 Cr.
Expenditure stands at ₹542 Cr, which is 46.3% of the revised project cost.
Remaining budget: ₹629 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.