RailwaysIPM · Central Project +137.5% overrun#400019

DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS]

Ministry of RailwaysMaharashtra
Revised Cost: ₹1171 CrUtilization: 47.9%Overrun: +₹678 Cr

Original Cost

₹493 Cr

Baseline estimate

+138% overrun

Revised Cost

₹1171 Cr

Latest approved cost

Expenditure

₹560 Cr

Spent to date

Utilization

47.9%

Of revised budget

Escalated

Cost Status

+137.5%

+₹678 Cr increase

Remaining

₹611 Cr

Budget left

Budget Utilization

47.9%
0%25%50%75%100%

Spent

₹560 Cr

Remaining

₹611 Cr

Total

₹1171 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹493 Cr

Revised Cost

₹1171 Cr

Increase

+₹678 Cr

Escalation

+137.5%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/12/2026

Revised Completion

30/09/2027

Completed

Project Details

Project Code400019
SectorRailways
MinistryMinistry of Railways
StateMaharashtra
Data Month2026-06

Financial Summary

Original Cost₹493 Cr
Revised Cost₹1171 Cr
Expenditure₹560 Cr
Original End Date31/12/2026
Revised Date30/09/2027

Project Intelligence

Cost has increased by ₹678 Cr (137.5%) from the original estimate of ₹493 Cr.

Expenditure stands at ₹560 Cr, which is 47.9% of the revised project cost.

Remaining budget: ₹611 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS] is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹493.00 Cr, later revised to ₹1170.83 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS]"?
DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS] is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Maharashtra. Original cost: ₹493 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹493 Cr and has been revised to ₹1171 Cr — a cost overrun of +137.5%. Expenditure to date: ₹560 Cr (47.9% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS] is under the Ministry of Railways in the Railways sector. Project code: 400019. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. DHULE [BORVIHIR] - NARDANA NEW LINE [50.60 KMS] is one of several Bihar projects tracked under the Railways sector on the IPM system.