RailwaysIPM · Central Project +24.1% overrun#617374

Dallirajhara - Rowghat New Rail Line Project, Phase-I

Ministry of RailwaysChhattisgarh
Revised Cost: ₹1881 CrUtilization: 114.5%Overrun: +₹365 Cr

Original Cost

₹1516 Cr

Baseline estimate

+24% overrun

Revised Cost

₹1881 Cr

Latest approved cost

Expenditure

₹2155 Cr

Spent to date

Utilization

114.5%

Of revised budget

Escalated

Cost Status

+24.1%

+₹365 Cr increase

Remaining

₹0 Cr

Budget left

Budget Utilization

114.5%
0%25%50%75%100%

Spent

₹2155 Cr

Remaining

₹0 Cr

Total

₹1881 Cr

Budget Split

SpentRemaining

Cost Escalation Analysis

Original Cost

₹1516 Cr

Revised Cost

₹1881 Cr

Increase

+₹365 Cr

Escalation

+24.1%

Project Timeline

Project Approved

Construction / Implementation

Original End Date

31/03/2025

Revised Completion

28/02/2026

Completed

Project Details

Project Code617374
SectorRailways
MinistryMinistry of Railways
StateChhattisgarh
Data Month2026-06

Financial Summary

Original Cost₹1516 Cr
Revised Cost₹1881 Cr
Expenditure₹2155 Cr
Original End Date31/03/2025
Revised Date28/02/2026

Project Intelligence

Cost has increased by ₹365 Cr (24.1%) from the original estimate of ₹1516 Cr.

Expenditure stands at ₹2155 Cr, which is 114.5% of the revised project cost.

Remaining budget: ₹0 Cr. Tracked under the DPIIT Investment Project Monitoring system.

Sector: Railways. Ministry: Ministry of Railways.

Dallirajhara - Rowghat New Rail Line Project, Phase-I is a centrally-funded infrastructure project under Ministry of Railways, in the Railways sector. The original approved cost is ₹1516.00 Cr, later revised to ₹1881.26 Cr.

This project is tracked under the Investment Project Monitoring (IPM) system maintained by DPIIT. Other central projects in the same sector are listed below.

?

Frequently Asked Questions

QWhat is IPM project "Dallirajhara - Rowghat New Rail Line Project, Phase-I"?
Dallirajhara - Rowghat New Rail Line Project, Phase-I is a centrally-funded infrastructure project under the Ministry of Railways, tracked through the Investment Project Monitoring (IPM) system. Sector: Railways. State: Chhattisgarh. Original cost: ₹1516 Cr.
QWhat is the cost overrun for this Bihar IPM project?
The original cost was ₹1516 Cr and has been revised to ₹1881 Cr — a cost overrun of +24.1%. Expenditure to date: ₹2155 Cr (114.5% of revised cost). Data as of 2026-06.
QWhich ministry is responsible for this project?
Dallirajhara - Rowghat New Rail Line Project, Phase-I is under the Ministry of Railways in the Railways sector. Project code: 617374. Bihar is one of the states tracked under the central IPM dashboard for this project.
QWhat is the IPM dashboard and what does it track?
The Investment Project Monitoring (IPM) dashboard, maintained by DPIIT (Department for Promotion of Industry and Internal Trade), tracks centrally-funded infrastructure projects worth ₹150 Crore and above. Dallirajhara - Rowghat New Rail Line Project, Phase-I is one of several Bihar projects tracked under the Railways sector on the IPM system.