Original Cost
₹1516 Cr
Baseline estimate
Revised Cost
₹1881 Cr
Latest approved cost
Expenditure
₹2144 Cr
Spent to date
Utilization
114.0%
Of revised budget
Cost Status
+24.1%
+₹365 Cr increase
Remaining
₹0 Cr
Budget left
Spent
₹2144 Cr
Remaining
₹0 Cr
Total
₹1881 Cr
Original Cost
₹1516 Cr
Revised Cost
₹1881 Cr
Increase
+₹365 Cr
Escalation
+24.1%
Project Approved
Construction / Implementation
Original End Date
31/03/2025
Revised Completion
28/02/2026
Completed
Cost has increased by ₹365 Cr (24.1%) from the original estimate of ₹1516 Cr.
Expenditure stands at ₹2144 Cr, which is 114.0% of the revised project cost.
Remaining budget: ₹0 Cr. Project is tracked under the DPIIT Investment Project Monitoring system.
Sector: Railways. Ministry: Ministry of Railways.